Termites (deemak) in a Bihar house: when to treat, how, and what it costs later
Abhishek Ranjan, Diploma Civil Engineer · checked against IS 6313 Parts 2 and 3, 12 Nov 2026
The short answer
Treat the soil while it is still open. Once the floor and tiles are down, the only way in is a hole every 300 mm.
1Bottom and sides of the foundation trenchStage 4, neev: just before the foundation concrete
2Backfill against the foundation wallAs the earth goes back, layer by layer
3Top of the plinth fillingStage 5, with the DPC: before the floor base
4Joint between walls and floorSame day as 3, through a small channel
5Soil along the outside wallsWhen the house is complete
Termites in Bihar come up from the soil, not through the air. A treated layer of soil around and under the house stops them. It only works if it is complete and continuous: one missed corner is their way in.
5 L/m²
Flat soilTrench bottom and sides, plinth fill top. IS 6313 Part 2.
7.5 L/m²
Soil against wallsBackfill, wall-floor joint, outer edge.
300 mm
Later: one hole per footDrilled through your floor along every wall. IS 6313 Part 3.
Where the treated soil goes
Not to scale. Rates are litres of mixed solution per square metre, from IS 6313 Part 2. With an RCC column footing, treatment along the column and plinth beam starts 500 mm below ground instead of at the trench bottom.
Why the timing is everything
The same job, before the floor and after the tiles
Before the floor, the soil is open and a mason with a hand sprayer reaches every part of it. After the tiles, the soil is under concrete, and the chemical goes in only through holes.
Before the floor: spray the trench, the backfill and the whole plinth fill. A continuous layer, one day's work per stage.After the tiles: drill, pump, seal, hole by hole. The soaked patches may not join, and soil under platforms, steps and pipes is hard to reach.
1They come from below
The termites that damage Bihar houses nest in the soil and need its moisture. They build mud tubes and tunnels from the nest up to wood. The standard calls the treated soil a chemical barrier between the ground and the woodwork.
2A barrier must have no gaps
IS 6313 Part 2 says the barrier must be complete and continuous under the whole structure, and every part must get the full dose. That is easy on open soil and close to impossible through holes in a finished floor.
3Later costs more and covers less
After tiles you pay for drilling, the chemical, sealing and tile patches, and furniture has to move. Damage already done to frames and cupboards is extra. The standard also asks for follow-up checks in the humid season.
The rule for your house: start the treatment when the neev trench is ready for concrete (stage 4) and finish it before the floor base goes on the plinth filling (stage 5, with the DPC). Details by stage: DPC and deemak treatment.
Already living there?
Six signs you already have deemak
The damage is usually inside the wood, so look for these. The last one is a different insect and needs a different treatment.
Mud tubes on walls
Thin brown lines, pencil-wide
Running up the plinth, a wall, a door frame or behind a cupboard. Break one: if it is hollow and has pale insects, termites are active. IS 6313 Part 3 calls these shelter tubes.
Hollow door frame
Tap it: a dull, papery sound
Termites eat the inside and leave the painted surface. Press the lower part of the chaukhat with a screwdriver; if it sinks in, the frame is eaten.
Wings after the first rains
Swarms at lights, wings on the sill
Winged termites fly after a few warm days followed by rain, in the monsoon or just after it. Wings dropped indoors point to a colony close by, says IS 6313 Part 3.
Bubbling near the floor
Blisters on paint or wood, close to the ground
Termites tunnel just under the surface, often with damp. Also check skirting and the back of fixed cupboards. If you only see damp, read seelan.
Paper and cardboard eaten low down
Bottom shelf, boxes, books, sacks
Things kept on the floor or the lowest shelf go first, often with soil stuck to them. Keep stored goods off the floor and away from walls.
Pellets or powder under wood
Not soil termites: drywood termites or borers
Soil termites don't turn wood into powder. Pellets point to drywood termites, which IS 6313 Part 3 notes in the interior of eastern India, or wood borers. Soil treatment won't stop these; the wood itself is drilled and treated.
New house · how it is done
The five steps, in the order your house goes up
These are the steps and doses of IS 6313 Part 2, the national code for treating soil before construction. Your mason can do them with a hand sprayer or watering can, or a pest-control firm can. Either way, ask how many litres of mixed solution go into each step.
Where
Dose
1. Trench bottom and sidesUp to about 300 mm up the sides. Brick (masonry) foundations. IS 6313-2, 7.2.1
5 L/m²
2. Backfill against the foundationPer m² of wall face, each side, sprayed in the same layers the earth goes back in. 7.2.2
7.5 L/m²
2. RCC column footing insteadSoil against columns and plinth beam, from 500 mm below ground upward. Dense concrete is not entered, so the trench bottom is skipped. 7.3
7.5 L/m²
3. Top of plinth fillingBefore the sand bed or floor base. 7.4
5 L/m²
4. Wall-floor joint30 × 30 mm channel along every wall and column inside, rod holes 150 mm apart down to ground level. 7.5
7.5 L/m²
Pipes entering the soilLoosen soil 150 mm around each pipe, 75 mm deep, then treat. 7.9
same dose
5. Outer strip, house completeRod holes 150 mm apart, 300 mm deep, along every outer wall. Full depth if the fill outside is deeper than 300 mm. 7.6
7.5 L/m²
Under an apron (outer path)Top of the rammed earth before the apron is laid. 7.7
5 L/m²
Rules that decide whether it works
Dry soil only. No treatment while it rains or when the soil is wet with rain or ground water. A waterlogged trench is pumped out first and treated once the soil absorbs again.
Wait before covering. Concrete goes on only once the spray has soaked in and the surface is dry.
Don't disturb it. If treated soil is dug up later (a new pipe, a drain), treat it again at once.
The dose is mixed solution. The doses above are litres of diluted chemical, not of the bottle. Dilution is on the label; see the calculator.
Keep a record. Write down the date, the chemical, the dilution and the litres used at each step.
Muzaffarpur and north Bihar
Four things to plan for on a north Bihar plot
The generic guides skip these. Each one comes straight from a line in the standard that matters more here than elsewhere.
Wet trenches
With high ground water and monsoon rain, neev trenches here often hold water. The standard does not allow treatment on soil wet with rain or ground water.
Dig the neev in the dry months if you can. If water collects, pump it out and treat only when the soil soaks up the spray again. See plinth height in flood areas.
The chapakal and borewell
Most compounds have a handpump or borewell close to the house. The standard says to avoid these chemicals where wells or water supplies could be contaminated.
Mix and wash the sprayer far from the handpump and drains. Never pour leftover solution on the ground near it. Keep the concentrate locked away from children and animals.
Old orchard or bamboo land
Many new plots around Muzaffarpur were litchi or mango orchards or bamboo clumps. Roots, stumps and buried wood are food for termite colonies right under your floor.
IS 6313-2 asks for trees, stumps, logs and roots to be removed and the plot cleared of debris before treatment. If you find a termite mound inside the plinth, break it open and soak it first.
Wood that comes later
Soil treatment does not protect against drywood termites, which the standard notes in eastern India. Your chaukhats and cupboards need their own care.
Buy seasoned, treated frames. Keep wood off the floor and off damp walls, and paint or polish all faces, including the back that touches the wall: painting wooden doors.
What it costs later
If the house is already built: what post-construction treatment involves
It can still be done, and it is worth doing as soon as you see mud tubes. But compare the work.
Before the floor
After tiles and doors
How the chemical gets in
Sprayed on open soil and backfill
Pumped into 12 mm holes, about 300 mm apart, along every wall
Coverage
The whole area under the house, continuous
Patches around each hole; hard under platforms, steps, bathrooms and pipes
Your floor
Not laid yet
Holes through tiles at the wall edge, sealed and patched; furniture moved
Wood
New, so it can be bought treated
Frames already eaten get drilled and injected, or replaced
Cost
Chemical + a few hours per stage: Ask rate
A firm's quote per sq ft, plus repairs: Ask rate
The work, as IS 6313 Part 3 lays it out
Inspect firstFind how far it has spread and where they enter: plinth, wall-floor joint, door frames, switch boards, behind wooden panels. Remove all mud tubes so new ones show.
Outside wallsShallow channel along the wall, soil treated to 300 mm deep at 7.5 L/m² of wall face. Through a concrete apron: 12 mm holes 300 mm apart, 2.25 litres per running metre.
Floor inside12 mm holes at the wall-floor joint and at cracks and joints, 300 mm apart, chemical pumped in until it stops taking (up to 1 litre a hole), then sealed.
Walls at plinth levelHoles drilled at about 45°, from both sides, 300 mm apart, at corners and where frames sit in the wall.
The wood and fittings
Where wood meets masonry6 mm holes at 45°, up to half a litre each, then sealed.
Infested chaukhats and shelves3 mm holes slanting into the core, at least 150 mm apart over the whole frame, chemical infused. Bare wood gets two coats.
Wood beyond repairReplaced, and the new timber dipped or brushed twice with the chemical.
Switch boxesCovers off, inside dusted with 5% malathion powder.
The standard also asks for checks in later hot, humid seasons. Ask any firm, in writing, which chemical, what dilution, how many holes and litres, and what they do if termites return.
How much chemical
Litres for your house, by the standard
Put in your plinth size. The calculator applies the IS 6313 Part 2 doses to each step. Use it to buy the right amount, or to check a quote: if a quote names only a few litres for a whole house, ask how it was worked out.
Mixed solution needed
1Trench bottom + sides—5 L/m²
2Backfill against foundation—7.5 L/m² of wall face, each side
3Top of plinth filling—5 L/m² of floor area
4Wall-floor joint—7.5 L/m², inner wall faces, ground up to fill level
5Outer strip—7.5 L/m², 300 mm deep along outer walls
Total mixed solution——
Chlorpyrifos 20 EC, if used at 1%—1 part chemical + 19 parts water. For imidacloprid or bifenthrin products, use the dilution on the label; the litres of mixed solution stay the same. Price: Ask rate
If you wait until after the tiles: about — holes drilled along your walls inside and out, at 300 mm spacing.
An estimate from the standard's doses: columns, steps and an apron add more. Buy step by step, since the steps are weeks apart. Full material list for this stage: DPC and deemak material.
For stages 4 and 5
What we supply for this part of the house
Termite treatment
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Deemak se ghar kaise bachaye? (How do I protect my house?)
Treat the soil while it is open: the trench before the foundation concrete, the backfill, the top of the plinth filling before the floor base, and the wall-floor joint. Finish with the outer strip when the house is complete. Then keep wood off the ground and away from damp walls.
Anti-termite treatment kab kare? (When should it be done?)
Start at stage 4, when the neev trench is ready for concrete, and finish at stage 5, before the floor base goes on the plinth filling. The outer strip is done once the house is built. Never while it rains or on wet soil.
What are the signs of termites?
Mud tubes on walls and frames, a door frame that sounds hollow, wings on sills after the first rains, blistering near the floor, and paper eaten on the bottom shelf. Pellets or powder under wood point to drywood termites or borers instead.
How is it treated after the house is built?
By drilling: 12 mm holes about 300 mm apart where the floor meets the walls and along the outside, chemical pumped in until the soil stops taking it, holes sealed. Infested frames are drilled and injected. It is the method in IS 6313 Part 3, and it leaves gaps where you can't drill.
Which wood do termites go for first?
Wood that touches the floor or a wall at ground level: chaukhats, fixed cupboards and shelves, plywood skirting, and paper or cloth stored low. Concrete and steel aren't eaten, but termites reach wood through cracks and joints.
Is a pest-control spray enough?
No. A spray kills the termites you see; the colony is in the soil and comes back. The soil around and under the house needs a barrier: by spraying open soil in a new house, or by drilling and injecting in a finished one.
Can my mason do it?
Yes, with care. The standard names a hand compression sprayer or watering can and gives the doses, so the work is simple. The care is in the chemical: gloves and a mask, no smoking while mixing, nothing near the handpump, leftover solution never poured out. If you hire a firm, ask for the litres per step in writing.
Which chemical? Is lindane OK?
Use one listed in IS 6313 and labelled for termite control in buildings: chlorpyrifos 20 EC (used at 1%) or a newer imidacloprid or bifenthrin product at its label dilution. Lindane was in the 2001 code but was dropped from later editions; don't use it.
Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures
Civil engineer at our Reva Road store, Muzaffarpur, helping families plan the neev, plinth and slab. Every dose on this page was checked against the Bureau of Indian Standards codes on 12 Nov 2026. Send photos of your trench or your mud tubes on WhatsApp, and we'll look at them with you.
Bureau of Indian Standards, IS 6313 (Part 3):2001, post-constructional treatment: inspection, 12 mm holes at 300 mm, 1 litre a hole, 2.25 L per metre through an apron, wood and switch-box treatment, follow-up checks, the note on termites (shelter tubes, swarming after rain, drywood termites in eastern India).
Later editions of IS 6313 Part 2 (2013, 2022) dropped lindane and added imidacloprid and bifenthrin; dilution for those follows the product label.