Electrical check before plaster: pipe routes, box depths, the earth wire run, and a photo of every wall

Do this the evening before the plaster mason starts
  1. 1Pipe routes: every point has a pipe, runs go straight, no more than four bends between boxes, a pull wire in each.
  2. 2Box depths: each box face sits where the plaster face will be, or the tile face on tiled walls.
  3. 3Earth wire run: a pipe from the earth pit to the DB, and every pipe big enough for three wires.
  4. 4Photos: one of each wall, room name chalked on it, sent to us on WhatsApp and kept for life.

Wire, switches and the board can all be changed after plaster. These four can't, without cutting the new wall. Walk every room with your electrician and this sheet. It takes about an hour for a two-room floor.

4 bends
At most, box to boxMore than four quarter bends and the wire won't pull (CPWD).
12 / 25
mm in front of the brickBox face for plain plaster, and for plaster plus tile. Usual practice.
3 wires
In every pipe's countPhase, neutral and earth. Size the pipe for all three.

This is stage 2 of our four-stage wiring checklist, done in full. Wire sizes and MCBs come later, after plaster: wire amps chart · which MCB for which load. The ten mistakes we see most: common wiring mistakes.

One wall, the night before plaster
A bedroom wall before plaster, with the four things to check marked Brick wall under the roof slab. A pipe drops straight down from the slab to a switch board box beside the door, and another straight down to a socket box. Guide dots of plaster on the wall show where the plaster face will be. A pipe runs down at the corner to the floor for the earth lead toward the pit outside. The room name and wall are chalked on the brick, and a tape stands up from the chalked floor line. Numbers 1 to 4 mark pipe routes, box depth, earth run and the photo. door to earth pit BED 1NORTH 1 2 3 4 1 pipes run straight down from the slab 2 box face set to the guide dots (plaster line) 3 a pipe for the earth lead, down to the floor 4 wall named in chalk, tape up from the floor line, photo
Not to scale. The white dots are the mason's guide dots (thiya): the plaster face will touch them, so the boxes are set to them.
1
Check 1 of 4

Pipe routes

What can't be changed after plaster: where a pipe goes and how it bends.
0 of 9
What it costs after plaster

A diagonal pipe, or a run with six bends. The diagonal gets a nail through it the day someone hangs a TV. The six-bend run jams halfway when the wire is pulled, and by then the wall is plastered: the only fixes are cutting a new groove or a surface casing.

How many wires fit in one pipe

Wire size20 mm pipe25 mm pipeSo, per pipe
1.5 sq mm4 wires8 wires20 mm: one light circuit · 25 mm: two
2.5 sq mm3 wires6 wires20 mm: one socket circuit, full · 25 mm: two
4 sq mm2 wires5 wiresAn AC line on 4 sq mm needs 25 mm

CPWD Table I, the column for pipes with bends. Three wires per circuit: phase, neutral, earth. Pipe size is the outside diameter printed on the pipe.

Right and wrong runs
Pipe routes that can be found later, and ones that can't Left wall, marked right: pipes go straight up from the switch board and the socket to the slab, and the shaded strips above and below each box show where not to drill. Right wall, marked wrong: one pipe cuts diagonally from the board to a far socket and another wanders across the middle of the wall. Below: a gentle bend marked right, a sharp kinked bend marked wrong, and a count of four bends between boxes. ✓ STRAIGHT yellow = don't drill here (in line with a box, under slab) ✗ SHORTCUTS a nail for a frame or TV finds it, nobody else can BENDS gentle, 7.5 cm+ ✓ cut and folded ✗ 1234 four bends, box to box: the most; a fifth needs a box
The yellow strips are usual practice, not a code rule: if every pipe runs straight from its box, you know where not to drill for the life of the house.
2
Check 2 of 4

Box depths and positions

What can't be changed after plaster: how deep each box sits and where.
0 of 8
What it costs after plaster

A box set to the brick, not the plaster line. After plaster it sits 12 mm deep in a hole; on a tiled wall, 25 mm. The plate rocks, the screws are too short, and moving the box means cutting fresh plaster or tiles around it.

Where the box face goes
Box depth on a plain wall, on a tiled wall, and the wrong way Three side views of a wall. Plain wall: brick, about 12 mm of plaster, box face level with the plaster face, marked right. Tiled wall: brick, plaster and tile together about 25 mm, box face level with the tile face, marked right. Wrong: box face level with the brick, so after plaster it sits in a hole and the screws do not reach. PLAIN WALLTILED WALLWRONG ✓✓✗ 12 plasterfacebrick 25 tileface platescrewsdon'treach Figures: mm in front of the brick, usual practice.Ask your mason how thick he will plaster.
On a tiled wall, decide the tile before the boxes go in: a thicker tile or a thick adhesive bed moves the face further out.
3
Check 3 of 4

The earth wire run

What can't be changed after plaster: the path the earth wire will take.
0 of 5
What it costs after plaster

No pipe left for the earth lead. It ends up clipped along the outside wall, where a mason's trowel or a rusty clip cuts it one day, and the whole house's earth hangs on that one wire. Nothing shows until a geyser body goes live and the RCCB has nothing to work with.

The earth path, pit to box
The earth wire path from the pit to the DB and on to each box Section through the house edge. The earth pit is in the ground outside. Its lead enters the wall low down in a pipe and rises to the DB's earth bar. From the DB a pipe carrying red, black and green wires runs to a switch box, where the green wire ends on the earth stud. Labels say the pipe for the lead is laid before plaster and floor, and every pipe is sized for three wires. earth pit DB earth bar earthstud pipe for the lead:laid before plasterand floorfloor3 wires per circuit
Green is earth. The pit itself (rod or plate, how deep, how tested) is on earthing basics; this check is only about leaving the way in.
4
Check 4 of 4

Photos of every wall, on WhatsApp

What can't be done after plaster: seeing where the pipes are.
0 of 6
What it costs after plaster

Photos taken the morning after the first coat. They show grey plaster and nothing else. The photo has to be taken the evening before, and it is free.

A photo that will still help in ten years
How to photograph a wall before plaster A phone screen showing a brick wall from floor to slab. The room name and wall are chalked on it, a yellow tape stands up from the chalked floor line beside the switch board, and the pipes and boxes are visible. Beside it: what each photo must show. BED 1 NORTH 1234 room + wallchalked big floor lineand a tape up slab to floorwhole wall in daylight,phone level
Send the photos to 90310 74624 the evening before the mason starts. Put the house name in the first message.

Send us what's still open

We'll look at the unticked items and your wall photos with you, and send any pipes, boxes or bends still needed with today's price.

Send to Sashikesh
0/9Pipe routes
0/8Box depths
0/5Earth run
0/6Photos

Your ticks stay on this phone only. Nothing is sent until you press the button. The printed sheet has lines for the electrician's and your signature.

Questions people ask us

Short answers

What has to be done before plaster? (plaster se pehle kya karein)

Everything that sits inside the wall: every pipe and box in place, the pipes straight and not over-bent, a pull wire in each run, boxes set to the plaster face, the pipe for the earth lead laid, and a photo of each wall. Wire, switches and the board come after plaster.

How deep should the switch box be set?

So its front edge is level with the finished wall. CPWD's specification says switch boxes are mounted flush. With inside plaster of about 12 mm, the box stands about 12 mm in front of the brick; on a wall getting tiles, about 25 mm, to meet the tile face. Both are usual practice: ask your mason what thickness he will plaster.

How many wires go in a 20 mm pipe?

CPWD's table for pipes with bends: four of 1.5 sq mm, three of 2.5 sq mm, or two of 4 sq mm. A circuit is three wires with the earth, so a 20 mm pipe takes one light or one socket circuit. For two circuits, or an AC line on 4 sq mm, use 25 mm. 20 or 25 mm

Does the earth wire go in the same pipe?

Yes. CPWD's specification has the earth wire drawn inside the pipe of every circuit and ended on the earth terminal in the switch box, and IS 732 makes it the same size as the phase. That is why the pipe size has to allow for it now. Sizes: wire amps chart · MCBs: which MCB for which load.

Something was missed and the wall is already plastered. What now?

Fix it before putty, not after paint. A short groove cut in fresh plaster and patched costs a day; after putty and paint it costs a repaint of that wall. If cutting isn't possible, the run goes on the surface in a casing. Concealed or surface

Is a mesh strip over the grooves needed?

It is usual practice, not a code rule. Plaster over a filled groove often cracks along the pipe line as it dries; a strip of wire mesh nailed across the groove before plaster holds it. Ask your mason; we can order the mesh.

Will you come to the site to check?

We don't promise site visits. Send photos on WhatsApp before plaster, one per wall with the room name chalked on it, and we will look at them with you.

Sashikesh Kumar
Diploma in Electrical, Tashya Ventures

Looks after wires, switchgear, inverters and pumps at our Reva Road store, Muzaffarpur. The figures on this page were checked on 13 Nov 2026 against CPWD's General Specifications for Electrical Works and IS 732. Where a figure is our usual practice rather than a rule, the page says so.

Where the figures come from

  1. Central Public Works Department, General Specifications for Electrical Works, Part I (Internal), 2013: 3.15 (switch box bottom 1.25 m from floor), 4.2.3 (metal boxes at least 1.2 mm / 18 gauge; earth stud in each box), 4.3.3 (pipes buried before plastering; switch boxes flush with the wall; GI fish wire 1.6 or 1.2 mm), 5.2.3 (PVC boxes: 2 mm walls, at least 60 mm clear depth), 5.3.1 (joints cemented, no damaged pipe; bend radius at least 7.5 cm; not more than four quarter bends outlet to outlet), 5.3.3 (fixing in the chase at most 60 cm apart, 15 cm either side of a bend), 5.3.4 (earth wire drawn inside the pipe in every circuit), Table I (wires per pipe).
  2. IS 732 (code of practice for electrical wiring installations): earth wire the same size as the phase wire.
  3. Plaster thickness (about 12 mm inside, 18 mm outside, about 25 mm for plaster plus wall tile), box heights, straight runs, mesh over grooves and the photo method: usual practice in Muzaffarpur houses, labelled as such on the page, and the same figures our other pages use.

Send us your wall photos

Sashikesh will look at them with you before the plaster mason starts, and send anything still needed with today's price on WhatsApp.