Best cement for chhat dhalai: which UltraTech bag for your roof slab, and why

The short answer

You do not need OPC 53. Every one of these bags reaches a normal M20 slab. What decides your slab more than the bag is the water in the mix, the vibrator and the curing.

M20
Concrete for an RCC slabThe lowest grade IS 456 allows for RCC. Usually 1:1.5:3.
10–14 d
Wet curing, blended cementAll four bags above are blended. IS 456.
200 ml
WP+200 per 50 kg bagIf you want waterproofing in the mix. UltraTech.
Pick the bag in two questions
Choosing cement for a roof slab Question 1: will the bare slab face a monsoon before the next floor, or is the plot low and damp? Yes: Weather Plus, with a Hi-Flex coat on top once cured and dry. No: question 2, do you want a step up from the everyday bag for the frame? Yes: Premium or Super. No: plain PPC, cured fully. Whichever bag: M20 mix, at most 25 litres of water a bag, vibrator everywhere, 10 to 14 days wet curing. 1 Will the bare slab face a monsoonbefore the next floor goes up,or is the plot low and damp? next floor a year or more away = yes NO YES WeatherPlus water-repellent cement+ Hi-Flex coat on toponce cured and dry 2 Want a step upfrom the everydaybag for the frame? slab, beams and columnsare poured only once YES NO Premiumor Super the usual slab bags UltraTech names both for slabs PlainPPC also makes a soundslab: cure it fully Whichever bag: M20 mix · ≤ 25 L water a bag vibrator everywhere · 10–14 days wet
Bag uses: UltraTech's own product pages. Water limit: IS 456 nominal mix for M20. Curing: IS 456 for blended cement.
The question everyone asks

"Use OPC 53 for the roof." Why we don't say that

Most "best cement for roof" pages end with OPC 53. Even UltraTech's own OPC-vs-PPC article lists "for slabs, columns, and beams: OPC" and, two lines later, "for hot climates: PPC". A Muzaffarpur slab poured in May is both. Here is how to read that.

153 is the cement's grade, not your slab's

The grade is the strength of a test cube of the cement alone at 28 days. Your slab is concrete, drawn as M20, and whether it gets there depends on the water, the vibration and the curing. A watery, badly cured OPC 53 slab ends up weaker than a blended one done properly.

2Heat is the enemy in a Bihar summer

OPC gains strength fast and gives off more heat while it sets. UltraTech warns that this heat "can cause cracks if curing is not done properly". Blended cements (fly ash or slag) start slower, give off less heat, stay workable longer in the sun, and keep getting denser after 28 days.

3Where OPC 53 really helps

When shuttering must come off fast, as on a builder's schedule. On a family house the props stay 14 days anyway. We keep blended bags. If your engineer has written OPC 53 on the drawing, we can order it for you; ask on WhatsApp for the time it takes.

How a slab gains strength
Strength gain of OPC and blended cement concrete Schematic. OPC 53 concrete rises steeply in the first week then flattens. Blended cement concrete rises more slowly, reaches the M20 line by 28 days and keeps rising. A third, dotted curve shows blended concrete whose curing stopped on day 3: it flattens below the M20 line and never reaches it. A shaded band marks the first 14 days, when the slab must be kept wet. keep wet 10–14 days M20 target 071428 days56 days after dhalai → slab strength → blended (our bags) OPC 53 curing stopped on day 3: never reaches M20
Shape only, not measured values. Both cements reach M20 by 28 days if kept wet. Stop the water early and no bag gets there.
  • The picture to remember: the dotted line. A slab whose curing stops on day 3 never makes up the lost strength, whatever the bag cost.
  • Blended cement needs the longer count. IS 456 asks for at least 10 days of wet curing with blended cement, and 14 in hot, dry weather. OPC needs 7 and 10.
  • UltraTech agrees PPC works for a slab. Its own FAQ: "PPC can be used for RCC work, especially in residential buildings where long-term durability is important." More on OPC vs PPC.
Our four bags

Which UltraTech bag for which roof

All four are 50 kg blended cements. What each says below is UltraTech's own wording; where UltraTech says nothing, we tell you what to read on the bag.

Main slab

UltraTech Premium

UltraTech: "the perfect choice" for "slabs, columns, beams, and roofing"
Slag blendHigh 28-day strength
  • A blend of "high-reactive silica and slag", with "superior 28-day compressive strength", says UltraTech.
  • Resists sulphates and chlorides, which UltraTech says suits buildings near water. Useful on a high water table.
  • UltraTech does not print the grade on its site. On the bag: slag cement carries IS 455.
Our usual answer for a house slab that the next floor will cover.
Main slab

UltraTech Super

UltraTech: a "modified PPC" combining properties of OPC 53 and PPC
Modified PPCEarly strength
  • Higher early strength and crack resistance, says UltraTech. It lists concrete in slab, beam and column among its uses.
  • Also for brickwork and plaster, so one bag can do the whole house.
  • Our Super batches come as PPC (IS 1489) or composite (IS 16415); the bag says which.
UltraTech says Super allows quicker removal of shuttering. On a house slab we still keep props 14 days.

UltraTech Weather Plus

UltraTech: a water-repellent cement that "effectively repels water"
Water-repellentDamp plots
  • UltraTech says it fills fine pores and breaks the paths damp travels by. It advises it for the whole house.
  • No grade on UltraTech's site. Our batches come as PPC or composite.
  • Mixed, poured and cured exactly like any other cement.
Not a roof coating. Hi-Flex still goes on top.

UltraTech PPC (plain bag)

The everyday bag, fly ash blended
PPCBest value
  • UltraTech: "PPC can be used for RCC work, especially in residential buildings".
  • Slower start, so the full curing and the full prop time matter most with this bag.
  • Our plain bags come as PPC (IS 1489) or composite (IS 16415).
Fine for a slab. Hard to beat for plaster and brickwork.
Read the bag before it goes on the vehicle
What to read on a cement bag A cement bag with five numbered marks: 1 product name, 2 cement type and IS code, 3 date of packing, 4 net weight 50 kg, 5 ISI mark with licence number. 50 kg ISI 1 2 3 4 5 1 Product name2 Type and IS code3 Date of packing4 Net 50 kg5 ISI mark Premium · Super ·Weather Plus PPC: IS 1489Composite: IS 16415Slag: IS 455OPC: IS 269 use within about3 months (usual practice) weigh a bag if in doubtwith CM/L licence number
The IS code tells you the cement type even when the product name doesn't. All our bags are checked at the counter with you.

Weather Plus or Premium? It depends on when the next floor goes up

North Bihar has a high water table and a long, heavy monsoon. Many families pour the roof in May or June and build the next floor a year or two later. That bare slab will stand through at least one full monsoon with water ponding on it.

  1. Next floor within a few months: Premium or Super. The new floor covers the slab before the rains matter.
  2. Slab stays the roof for a monsoon or longer: Weather Plus, then a Hi-Flex coat once the slab is cured and dry.
  3. Want waterproofing in the mix with Premium, Super or PPC: add WP+200, 200 ml per bag. With Weather Plus, take one or the other: UltraTech publishes no advice on using both together.
  4. Low or flood-prone plot: Weather Plus for the slab too, because damp comes from below as well as above.

One bag type for the whole pour. Don't start with one cement and finish with another because stock ran short. Count the bags with the calculator below and take them all before the morning. Today's price for each bag: cement rates. Cutting and delivery are charged separately; ask for the amount for your site, and see delivery.

Beyond the bag

Eight things that decide whether a slab leaks

The bag is one of them. The numbers on the drawing match the rows of the table.

Cross-section of a roof slab at the parapet A roof slab resting on a wall, cut through. 1 Hi-Flex coating on top, turned up the parapet. 2 The top slopes to the outlet. 3 Slab concrete. 4 Steel bars. 5 Cover blocks under the bars. 6 A honeycomb pocket from poor vibration, with water dripping through it. 7 Shuttering and props. 8 Rainwater outlet pipe through the parapet. 1 2 3 4 5 6 7 8 Not to scale. Bars and cover drawn larger than they are.
#WhatDo this
1Roof coatingConcrete alone is never fully waterproofHi-Flex, 2 coats at least 8 h apart, once the slab is cured and dry. Turn it up the parapet.UltraTech Weather Pro brochure
2SlopeStanding water finds every crackTowards the outlets, set in the top while the concrete is still soft.
3ConcreteOne bag type for the whole pourM20, usually 1:1.5:3. Water fixed before the day: at most 25 L per bag. WP+200 goes in here if you want it.IS 456 nominal mix · water per bag
4BarsStrength comes from the steel tooSizes and spacing exactly as on the engineer's drawing. Check before the pour.
5CoverBars near the surface rust and split itCover blocks under the bars, as on the drawing.IS 456: 20 mm mild, 30 mm moderate exposure · cover blocks
6VibrationAir pockets become leak pathsNeedle vibrator in every part, not only at the edges. Stop when bubbles stop.
7Shuttering, propsGaps let the cement slurry run outTight joints. Props stay 14 days with blended cement (next section).
8OutletFixed before the dhalai, not cut laterPipe set at the lowest point of the slope, through the parapet.

Before dhalai, send us photos. Send photos of the sariya on WhatsApp before dhalai and we'll check them with you; add the cover blocks and shuttering in the same photos. The full list for the morning is in the chhat dhalai checklist.

After the pour

Keep it wet two weeks, keep the props two weeks

All four of our bags are blended, so they get the longer counts in IS 456. These are the days that make the bag's quality count.

Curing and prop days for a roof slab with blended cement Day 0: pour from dawn; when the top is firm, cover with wet jute bags. Day 1: make bunds and flood the slab. Day 7: OPC could stop here, not our bags. Day 10: minimum wet curing for blended cement. Day 14: in hot, dry weather, stop curing now; props come out. Day 28: design strength reached; let the slab dry. Later: Hi-Flex coating, two coats eight hours apart. DAY 0DAY 1DAY 7DAY 10DAY 14DAY 28LATER Pour, starting at dawn Top firm: wet jute bags on Make bunds, flood the slab OPC could stop here Blended: the minimum Hot, dry weather: stop now Design strength reached Hi-Flex coating avoid the 12–4 pm heat in summer keeps sun and loo off; usual practice mortar or mud bunds; top up morning and evening not our bags (IS 456: 7 d, hot 10 d) IS 456, for blended cement IS 456 curing · props out today (14 days with blended: our practice) let the slab dry before coating 2 coats, at least 8 h apart keep the slab wet all through this blue stretch
WhatDays
Wet curing, blended cementPPC, composite, slag: all our slab bags. IS 456 cl. 13.5.110 days
Same, in hot, dry weatherA Bihar April to June. IS 45614 days
Wet curing, OPCFor comparison. IS 456: 10 days in hot, dry weather7 days
Props, slab span up to 4.5 mIS 456 cl. 11.3.1, written for OPC7 days
Props, slab span over 4.5 mIS 456 cl. 11.3.1, written for OPC14 days
Props, with our blended bagsIS 456 says to extend the times for other cements. We keep the longer figure unless your engineer sets one on site.14 days
May and June: the loo is the danger. Hot, dry wind pulls water out of a fresh slab in hours and leaves hairline cracks on the top. Pour from dawn, cover with wet jute bags as soon as the top is firm, and start flooding the next morning. How to make the bunds and how often to fill them: curing after chhat dhalai and dhalai in the heat. Prop times in detail: when to open the shuttering.
What goes wrong

Six mistakes that no bag can fix

Each picture shows the cause on the left and what you see later on the right. We hear about every one of these at the counter.

EXTRA WATER

Extra water "to make it flow"

You see: damp spots on the ceiling after rain

Water the cement doesn't need dries out and leaves fine pores, and pores are how water gets through. Fix the water per bag before the morning: we fix M20 at 25 L per 50 kg bag.

NO VIBRATOR

No vibrator, or only at the edges

You see: honeycomb patches when the shuttering comes off

Trapped air leaves pockets of bare stones. They weaken the slab and carry water straight through. Run the needle in every part until the bubbles stop.

3 d CURED 3 DAYS

Curing stopped after three days

You see: hairline map cracks on the roof top

The commonest mistake, and the costliest. A blended-cement slab needs 10 days wet, 14 in the heat. Paying for a better bag and then curing for three days wastes the better bag.

PROPS OUT

Props pulled out early

You see: a sag, or a crack across the middle of the ceiling

Blended cement gains strength more slowly in the first days. Keep the props the full 14 days. Hurry them out for the next job, and the slab carries its own weight before it can.

0 RAN SHORT

Ran short of bags in the middle

You see: a straight leak line where the pour stopped

Fresh concrete laid against concrete that has already set does not bond fully. Take every bag, all the same type, before the morning. If it happens anyway: if the dhalai stops midway.

DAMP FLOOR

Bags kept on a damp floor

You see: hard lumps, and weak concrete

Cement starts setting with any moisture. Stack bags on planks or plastic, away from walls, covered. Bring them close to the day and use them within about three months of packing: how old can cement be.

How many bags

Cement, balu and gitti for your slab

Put in the slab size. M20 at 1:1.5:3, the usual mix for a house slab. For 1000 sq ft that is about 77 bags at 4 inch, 96 at 5 inch and 115 at 6 inch. The working is in how many bags for a chhat dhalai.

Slab area: — sq ft · thickness from your engineer's drawing: how thick a lenter

Your list

UltraTech Premium, 50 kg—Dry volume = wet × 1.54; cement = 1 part in 5.5 (usual practice). Add 2–3 bags spare.—
Balu (sand)—1.5 parts
Gitti, 20 mm—3 parts
Water, most allowed—25 L per bag at most (our site figure for M20). Less is better if the vibrator can still work it.
WP+200—200 ml per 50 kg bag (UltraTech)—
Hi-Flex, 2 coats—14–15 sq ft per kg; we use 14 so you don't run short (UltraTech). Parapet foot extra.—
Material totalAsk rate
Send this list on WhatsApp

Slab only: beams, chhajja and stairs are extra. Prices are filled in from today's rate. Steel, binding wire and everything else for the day: chhat dhalai kit · any mix or part of the house: cement, sand and gitti calculator.

Questions people ask us

Short answers

Which is the best cement for chhat dhalai?

For a house roof slab in Bihar, UltraTech Premium or UltraTech Super. UltraTech names Premium for "slabs, columns, beams, and roofing", and calls Super a modified PPC with higher early strength. Take Weather Plus if the bare slab will face a monsoon before the next floor goes up, or the plot is low and damp. Plain PPC also makes a sound slab if it is cured for the full time.

Is OPC 53 grade necessary for a roof slab?

No. 53 is the strength of the cement's own test cube, not of your slab. A house slab is normally M20 concrete, and blended cements reach M20 by 28 days with fixed water, proper vibration and 10 to 14 days of wet curing (IS 456). OPC 53 helps mainly where shuttering must come off fast; in a Bihar summer its higher heat means more cracking if curing is thin.

UltraTech Weather Plus dhalai ke liye kaisa hai? (Is it good for a roof slab?)

Yes. It is a full cement, mixed, poured and cured like any other, and UltraTech makes it water-repellent. It is the right pick when the slab will stay bare through a monsoon or the plot is damp. It does not replace the roof coating: put Hi-Flex on top once the slab is cured and dry.

Is plain PPC good enough for a roof slab?

Yes. UltraTech itself says PPC can be used for RCC work, especially in houses. It starts slower, so keep it wet for at least 10 days (14 in hot, dry weather) and keep the props for the full time.

Premium or Super: which one for the slab?

Both are slab bags. UltraTech points Premium at slabs and roofing and says it resists sulphates and chlorides, which helps near water. Super is the one-bag choice if you also want it for brickwork and plaster. For the slab itself, pick either and use only that one for the whole pour.

How much WP+200 per bag of cement?

200 ml for every 50 kg bag, as UltraTech's Weather Pro brochure says. Mix the dry materials with half the water, add the WP+200 to the other half, then add that. 96 bags need 19.2 litres, so one 20 L can. With Weather Plus, take one or the other; UltraTech gives no advice on using both. More in WP+200 per bag.

Which cement for a small lanter?

Lanter (lenter) is the local word for a roof slab. A small one over a room or the stair cabin takes the same bag as a main slab: Premium or Super, or Weather Plus if it will stay open to rain. Same M20 mix, same water limit, same curing days.

How many bags for a 1000 sq ft roof slab?

With M20 at 1:1.5:3, about 77 bags for a 4 inch slab, 96 for 5 inch and 115 for 6 inch, for the slab alone. Beams, chhajja and stairs are extra. Use the calculator above for your own size.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Civil engineer at our Reva Road store, Muzaffarpur. Every claim about a bag on this page is UltraTech's own wording, checked on 12 Nov 2026; curing, prop and water figures are from IS 456. Where UltraTech says nothing, the page says so and tells you what to read on the bag.

Where the numbers come from

  1. UltraTech, UltraTech Premium: blend of high-reactive silica and slag, superior 28-day compressive strength, for slabs, columns, beams and roofing, resists sulphates and chlorides.
  2. UltraTech, UltraTech Super: modified PPC combining OPC 53 and PPC properties, higher early strength, quick removal of shuttering, slab, beam and column among its uses.
  3. UltraTech, UltraTech Weather Plus: water-repellent, fills pores, advised for the whole home. No grade stated.
  4. UltraTech, Difference between OPC and PPC: "for slabs, columns, and beams: OPC", "for hot climates: PPC", OPC heat "can cause cracks if curing is not done properly", PPC can be used for RCC.
  5. UltraTech, Weather Pro waterproofing brochure: WP+200 at 200 ml per 50 kg, added with half the water, packs 200 ml to 100 L; Hi-Flex 14–15 sq ft per kg, two coats at least 8 h apart, 12 and 24 kg.
  6. BIS, IS 456:2000 Plain and reinforced concrete: Table 5 (M20 lowest grade for RCC), water: 25 L per 50 kg bag (w/c 0.5, IS 456 limit for moderate exposure, which is what we use), cl. 11.3.1 (stripping times), cl. 13.5.1 (curing 7/10 days OPC, 10/14 days blended), cl. 26.4 (nominal cover).
  7. Our supplier invoices: Super and Weather Plus delivered as PPC and as composite (PCC) batches.

Send us your slab size and date

We'll send back the bags, WP+200 and Hi-Flex for your roof, with today's price, on WhatsApp.