Chhat dhalai checklist: what to check a week before, two days before, on the day, and after

The short answer
  1. 1 WEEK BEFORESteel and shuttering. Bars, cover blocks, chairs, plates, props, conduits and sleeves, checked against the drawing.
  2. 2 DAYS BEFOREMaterial, water, machines, people. Everything on site, covered, counted and booked.
  3. DHALAI DAYStart at first light, never stop. Same mix and water in every batch, vibrate every part.
  4. NEXT MORNINGCuring begins. Keep the slab wet and the props in place.

A dhalai goes well or badly because of the week before it. Concrete stiffens within hours, so on the day there is no time to fetch a missing bag or fix a prop.

20 mm
Under the slab barsUsual cover, held by cover blocks (IS 456, mild exposure). Follow the drawing if it says more.
25 L
Most water per bagWater-cement ratio 0.5. Less if the sand is wet.
10–14
Days of curingFor PPC and other blended bags. 14 in hot, dry weather.
The slab, just before the concrete
Section through a roof slab ready for concrete A brick wall on the left, shuttering plates on timber runners held up by props standing on planks with wedges and cross-bracing. On the plates: cover blocks under the bottom bars, a chair holding the top bars over the wall, a conduit with a fan box, a pipe sleeve, and edge shuttering marked with the slab thickness. Eight numbered checks are listed below the drawing. 125 mm 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Sariya: size, spacing, laps as drawn Cover blocks: bars kept off the plates Chairs: top bars held at height Plates: level, joints sealed, clean, oiled Props: on planks, wedges tight, braced Conduit, fan box: tied, ends taped Pipe sleeves and roof outlets placed Edge: slab thickness and slope marked
Not to scale. The dashed box is where the concrete goes. 125 mm is a common house slab (5 inches); your drawing decides. Cover: IS 456, Table 16.
A week before

Steel and shuttering: the eight checks in the drawing

Do these while there is still time to fix them. Once concrete covers a mistake, it stays in the roof. The numbers match the drawing above.

1

Sariya as per the drawing

Bar size, spacing, extra top bars over beams and walls, the chhajja bars, and laps away from the middle of the span. How to count them: sariya for a slab.

Tata Tiscon · Saluja Gold · binding wire
2

Cover blocks under the bottom bars

They keep the bars off the plates so concrete wraps the steel. Usual cover for a house slab is 20 mm (IS 456, mild exposure). Never bricks or stone pieces. See cover blocks.

Cover blocks: we can order them for you
3

Chairs under the top bars

Top bars over beams and walls do their work only at the top. Bent-bar chairs hold them up so feet on the day don't push them down.

Bent from 8 mm or 10 mm bar
4

Plates level, sealed, clean, oiled

Gaps leak cement paste and leave rough, weak patches. Sweep out sawdust, wire bits, nails and paper. Oil lets the plates come off clean.

5

Props firm and braced

Every balli or steel prop on a plank or brick base, never loose soil that softens when water spills. Wedges tight, bracing tied both ways.

6

Conduits and fan boxes

Tied to the bars, ends taped shut so concrete can't get in. Wiring cannot be added inside a slab later. See conduit before casting.

Conduit · fan box · round boxes
7

Pipe sleeves and roof outlets

For the toilet stack, the down-line and rainwater, so nobody drills the new roof. See pipe sleeves in the slab.

uPVC pipe · Prince · Ashirvad
8

Thickness and slope marked

Mark the top of the slab on the edge shuttering all round. If the drawing puts the roof slope in the slab, mark it falling towards the outlets.

Before you pour: send photos of the sariya on WhatsApp before dhalai and we'll check them with you. Once the steel is tied, photograph the mesh, the cover blocks and the props. It is a second pair of eyes, not a structural design: your engineer's drawing still decides.

Send steel photos
Two days before

Material, water, machines and people, all on site

Two days gives time to count and cover everything, without cement sitting long on a damp site. Material that arrives on the morning of the pour never gets checked.

Material

  • Cement on planks or a platform, off the ground, away from damp walls, covered. Stacks no higher than 10 bags (usual practice). Count the bags as they come off the truck.
  • Check the packing date on the bags; use cement within about 3 months of it (usual practice).
  • Balu and gitti on a clean patch, covered, never on mud.
  • WP+200, if you want waterproofing in the mix: 200 ml per 50 kg bag (UltraTech).
  • Two or three spare bags. Running short mid-pour is how cold joints happen.
  • Quantities: planner below or the full calculator.

Water and power

  • Store it before the day in drums or a tank. A power cut stops the motor, and the mixer cannot wait.
  • A 200-litre drum mixes about 8 bags at 25 litres a bag. Keep at least twice the mixing water for washing tools and the first curing.
  • One marked bucket for mixing water, so every batch gets the same amount.
  • Lights and a power point if the pour may run past dark.

Machines and people

  • Mixer and needle vibrator booked by date and time. The thekedar or shuttering contractor usually brings or hires them. Ask for a spare needle and fuel for the whole day. More: mixer and vibrator.
  • Labour named for every job in the table below, so nobody "comes later".
  • Tarpaulin or polythene ready in case of rain.
  • Forecast checked. No rain during the pour or the evening after.

Sand during the rains: Bihar's sand mining stops in the monsoon months, so balu gets scarce and dear. If your dhalai falls between June and October, buy and cover the balu early. Season advice: dhalai in the monsoon · dhalai in May–June heat.

Dhalai day

One direction, one mix, no stopping

The pour starts at the far corner and works back towards the stairs, so nobody walks on fresh concrete and the last strip is the nearest one.

Pour plan seen from above A rectangular roof divided into six strips. Strips 1 to 3, starting at the far end, are already poured. Placers are working on strip 4 with the vibrator operator just behind them. Strips 5 and 6 still show bare steel, with walking boards on chairs leading to the stair opening. The mixer and hoist stand on the ground beside the stairs. A props watcher stands under the shuttering. FAR END (START HERE) 1234 56 STAIRS POUR MOVES THIS WAY placers vibrator, just behind props watcher(below, under the plates) boards on chairs ON THE GROUND, BESIDE THE STAIRS mixer hoist
Strips are a way of working, not joints: each strip is poured against the still-soft edge of the last one.
  1. Start at first light. In May–June, aim to finish the top before the sun is high. Heat shortens the time concrete stays workable.
  2. Same mix and water in every batch. Usual practice for a house slab is M20, 1:1.5:3 by volume (cement : balu : gitti), unless your engineer writes otherwise. Water no more than 25 litres a bag. The last batch should look like the first.
  3. No water added "to make it easy". Watery concrete flows nicely and ends up weak, dusty and cracked.
  4. Tip it close, don't drop it. From a height the gitti separates from the paste. Keep the drop under about 1 metre (usual practice).
  5. Vibrate every part. Needle in at short spacing (usual practice 30–45 cm), 5 to 15 seconds each, until bubbles stop rising. Pull out slowly. Too long in one spot is also wrong.
  6. Pour in one direction without a halt. Each strip goes against the soft edge of the last. If a stop is forced, ask your engineer beforehand where the joint may go.
  7. Watch steel and props the whole time. Put back any bar or cover block that has been trodden flat. Stop if a prop sinks or a plate bulges.
  8. Finish, then protect. Level the top, keep the slope, and cover with wet hessian or polythene once it has stiffened, if sun or wind are strong.
Job on the dayWhat that person does
Mixer feedersCement, balu, gitti and the measured water, batch after batch
CarriersConcrete from the mixer to the roof, by tasla or hoist
PlacersTip concrete close to where it goes, never from a height
Vibrator operatorFollows the placers and vibrates every part
FinishersLevel the top and keep the slope to the outlets
Steel watcherLifts back bars and cover blocks pressed down by feet
Props watcherStays under the shuttering, watches props and plates, calls a stop
Water personKeeps drums full and stays at the mixer
If it rains during the pour. Light rain: keep going and cover the finished strips with polythene. Heavy rain washes cement out of fresh concrete: stop at a point your engineer has agreed, cover everything, and don't add cement on top afterwards. Before a monsoon dhalai, read dhalai in the monsoon.
What goes wrong

Skip a check, and this is what the roof shows later

Each picture shows the mistake on the left (in red) and the roof a year or a monsoon later on the right. All six are cheap to prevent and expensive to repair.

NO COVER

Bars on the plates, no cover blocks

You see: rust lines on the ceiling, then concrete falling off

With no concrete under them, the bars take in damp, rust and swell, and the ceiling cracks along each bar. Cover blocks of the drawing's size, under every part of the mesh.

LOOSE SOIL water stands here every rain

A prop on loose soil

You see: a dip in the roof where water stands

Water spilt on the day softens the ground, the prop sinks, and the slab sets with a sag. Every prop on a plank or bricks, wedges tight, braced both ways.

EXTRA WATER

Extra water in the mix

You see: fine cracks, a dusty top, a weaker roof

The extra water leaves tiny holes as it dries out. Fix the water per bag before the day (no more than 25 litres) and use one marked bucket.

NO VIBRATOR

No vibrator, or not everywhere

You see: honeycomb patches of bare gitti under the slab

Hand tamping leaves air around the bars. The honeycomb lets water reach the steel. Book a needle vibrator with a spare needle, and vibrate every strip.

STOPPED a seep line along the joint

Stopping halfway

You see: a line on the ceiling that seeps every monsoon

New concrete does not bond well to concrete that has already set: a cold joint. Spare bags, stored water and a spare needle remove the usual reasons for a stop.

>1 m DROPPED stones fall out, paste runs off

Concrete dropped from a height

You see: stony, porous patches

The heavy gitti lands first and the paste splashes away, so that spot has stones with nothing between them. Tip the tasla close to the surface.

After the pour

Curing starts the next morning. The props stay.

The job is not over when the last tasla goes up. The next two weeks decide how strong the roof gets.

The first three weeks after the dhalai Day 0 is the pour. Curing runs from day 1 to at least day 10 with blended cement, to day 14 in hot dry weather. Slab props: IS 456 gives 7 days for OPC on spans up to 4.5 metres; with blended cement we advise 14. Props for spans over 4.5 metres: 14 days. Beam props: 14 days up to 6 metres, 21 days beyond. No bricks or bags stacked on the new roof while the props are in. DHALAI 037101421 DAYS AFTER THE POUR Curing: keep it wet, no breaks from next morning · 10 days min · 14 if hot, dry Slab props, span up to 4.5 m IS 456 for OPC: 7 · with PPC bags we say 14 Slab props, span over 4.5 m 14 days, longer in cold weather Beam and chhajja props 14 up to 6 m span · 21 beyond · chhajja like a beam No bricks or bags on the new roof while props are in
Props: IS 456 clause 11.3 gives the OPC figures; blended cement gains strength more slowly, so we give the longer count. Your engineer can change it.

Curing: how and how long

Curing means keeping the slab wet so the cement keeps gaining strength. Start the next morning, once the surface takes water without the paste washing off. Make small mud or mortar bunds and keep water standing in them. Sprinkling twice a day is not curing: the slab must never dry out in between.

IS 456 asks for at least 10 days with blended cement and 14 in hot, dry weather. All our UltraTech bags (PPC, Super, Weather Plus) are blended, so 10 days is the floor. Full method: curing after dhalai.

Props and plates: don't hurry the carpenter

The shuttering contractor wants his plates back. Let him take side forms early, but the props under the slab and beams stay for the days in the chart. A slab that sags from early stripping cannot be fixed. Details for slab, beam and chhajja: when to remove shuttering.

The first rain and the first cracks

Fine surface cracks in the first days usually mean the top dried too fast. Keep curing; tell us what you see. Cracks right through, or along bars, need your engineer. More: cracks after dhalai.

Your order and your dates

What to have on site, and when

Put in the roof size and the dhalai date. You get the cement, balu, gitti, WP+200 and water for a plain slab, and the dates for each check. Steel comes from your drawing.

Roof area: — sq ft · mix 1:1.5:3 (M20, usual practice)
Pick a date to see when each step is due.

Your slab list

UltraTech cement, 50 kg—Super or Premium for the slab; Weather Plus if the roof stays open to rain. Plus 2–3 spare bags.Ask rate

Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.

Balu
—Clean, coarse, no mud. Wet balu bulks: measure it dry, or ask us.Ask today's rate
Gitti, 20 mm—Washed, no dust or clay lumps.Ask today's rate
UltraTech WP+200—200 ml per bag, in the second half of the mixing water (UltraTech).—
Water to store—25 L a bag for mixing, doubled for washing and the first curing. 200 L drums.
Sariya and binding wiredrawingFrom your engineer's bar list. How to count: sariya for a slab.
Material totalAsk rate
Send this list on WhatsApp

For a plain slab of even thickness. Beams under the slab add concrete: add them in the full calculator. The working is in how many bags for a slab. Cutting and delivery are charged separately; ask for the amount for your site (delivery).

Printable checklist

Print it, stick it on the site

One page for the thekedar and the family. Tick each line as it is done.

Chhat dhalai checklistTashya Building Solutions · WhatsApp 90310 74624 · tashyaventures.com
Dhalai date:Thekedar's phone:Slab size:Mixer / vibrator from:
1 week before: steel and shuttering
Sariya size, spacing, top bars, laps and chhajja bars as per drawing
Cover blocks under the bottom bars everywhereusual slab cover 20 mm; no bricks or stones
Chairs holding the top bars at height
Plates level, joints sealed, swept clean, oiled
Props on planks or bricks, wedges tight, braced both ways
Conduits and fan boxes tied, ends taped
Pipe sleeves and roof outlets placed
Slab thickness (and slope, if in the slab) marked on the edge
Steel photos sent on WhatsApp for a check
2 days before: material, water, machines, people
Cement counted, on planks, covered, packing date checked, 2–3 spare bags
Balu and gitti delivered and covered
WP+200 on site, if usedbags × 0.2 litre
Water stored in drums or tank; one marked bucket for mixing water
Mixer, vibrator, spare needle and fuel booked by date and time
Labour named for every job, including the props watcher
Forecast checked, tarpaulin and lights ready
Dhalai day
Start at first light
Same mix and water in every batchno more than 25 litres per bag
Tipped close, never dropped from height; every part vibrated
One direction, from the far end, no halt
Someone under the shuttering the whole time
Top levelled, slope kept, covered once stiff if sun or wind are strong
After
Curing from next morning: 10 days minimum, 14 if hot and dry
Slab props in for 14 days; beam props 14 to 21
No bricks or bags stacked on the roof while props are in

Figures: IS 456:2000 (cover, water-cement ratio, curing, props) and UltraTech (WP+200 dose). Your engineer's drawing and instructions come first.

Questions people ask us

Short answers

What should I check before chhat dhalai?

A week before: sariya size, spacing and laps as per the drawing, cover blocks under the bottom bars, chairs under the top bars, level and sealed shuttering, props on a firm base, conduits, fan boxes and pipe sleeves. Two days before: cement, balu and gitti on site and covered, water stored, mixer and vibrator booked with a spare needle, labour named for every job, and the forecast checked. The printable list runs in that order.

How many days before dhalai should the material arrive?

About two days before: time to count, cover and check the cement, balu and gitti, without the cement sitting long on a damp site. The steel should be tied and checked a week before, so there is time to correct it.

How much water in one bag of cement for the slab?

No more than about 25 litres per 50 kg bag, a water-cement ratio of 0.5 (standard figure, IS 456). Wet balu already carries water, so use less. Agree the amount with the mason before the day and measure it with one marked bucket.

Do I need a mixer and a vibrator for a house roof?

Yes. A mixer keeps every batch the same, and a needle vibrator removes trapped air that hand tamping leaves behind. The thekedar or shuttering contractor usually brings them or hires them for the day. Book both by date and time, with a spare needle and fuel. More in mixer and vibrator for dhalai.

When should the dhalai start in summer? (garmi mein dhalai kab)

At first light, so the top is finished before the sun is high. Wet the shuttering and keep the gitti in shade before you start. Full advice: dhalai in May–June heat.

How many days of curing after chhat dhalai? (chhat dhalai ke baad)

Start the next morning and keep the slab wet without a break. IS 456 asks for at least 10 days with blended cement such as PPC, which is what most bags in Bihar are, and 14 days in hot, dry weather. OPC needs at least 7. See curing after dhalai.

Should I add WP+200 to the slab concrete?

It is optional, and it helps a roof that will face the rain. The dose is 200 ml per 50 kg bag: mix the dry material with half the water, add WP+200 to the other half, then combine (UltraTech). A 100-bag slab needs 20 litres. It does not replace good compaction and curing. See waterproofing in the dhalai.

Can the pour be stopped halfway?

Avoid it. A stop leaves a cold joint, a weak line that often seeps later. Spare cement, stored water and a spare vibrator needle remove the usual reasons. If a stop cannot be avoided, ask your engineer beforehand where the joint may go. If it already happened: when the dhalai stops midway.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Answers the cement, steel and structure questions at our Reva Road store, Muzaffarpur. Every figure on this page was checked against IS 456 and the UltraTech sheets on 12 Nov 2026. Where other guides give different numbers, we give the safer one and say why.

Where the numbers come from

  1. Bureau of Indian Standards, IS 456:2000, Plain and reinforced concrete: Table 16 nominal cover (20 mm mild exposure); Table 5 maximum water-cement ratio (0.55 mild, 0.50 moderate; we use 0.50); clause 11.3 stripping times for OPC (slab props 7 days up to 4.5 m span, 14 beyond; beam props 14 days up to 6 m, 21 beyond); clause 13.5.1 curing (7 days OPC, 10 days blended cement, 14 suggested in hot dry weather).
  2. UltraTech Weather Pro brochure: WP+200 dose 200 ml per 50 kg bag, added to the second half of the mixing water.
  3. UltraTech product pages: Super described as a "modified PPC"; our Weather Plus bags are PPC or composite by the invoice codes. All are blended cements, hence the 10-day curing floor and the longer prop count.
  4. Tata Tiscon, 7 reinforcement checks before concrete pouring: clean bars, position and spacing, cover, stirrups, laps and binding, clean shuttering, weather.
  5. Usual-practice figures (M20 as 1:1.5:3, drop under 1 m, vibrator spacing, 10-bag stacks, cement within 3 months) are labelled where they appear. Other guides give 14–21 days of curing or 7 days for props; we follow IS 456 for blended cement and the longer prop count.

Send us your slab size and dhalai date

We'll send back the cement, sariya, balu, gitti and WP+200 for your roof with today's price, and plan the delivery for two days before.

TASHYABUILDING SOLUTIONS · MUZAFFARPUR
WhatsApp 90310 74624tashyaventures.com