With no concrete under them, the bars take in damp, rust and swell, and the ceiling cracks along each bar. Cover blocks of the drawing's size, under every part of the mesh.
A dhalai goes well or badly because of the week before it. Concrete stiffens within hours, so on the day there is no time to fetch a missing bag or fix a prop.
Do these while there is still time to fix them. Once concrete covers a mistake, it stays in the roof. The numbers match the drawing above.
Bar size, spacing, extra top bars over beams and walls, the chhajja bars, and laps away from the middle of the span. How to count them: sariya for a slab.
Tata Tiscon · Saluja Gold · binding wireThey keep the bars off the plates so concrete wraps the steel. Usual cover for a house slab is 20 mm (IS 456, mild exposure). Never bricks or stone pieces. See cover blocks.
Cover blocks: we can order them for youGaps leak cement paste and leave rough, weak patches. Sweep out sawdust, wire bits, nails and paper. Oil lets the plates come off clean.
Every balli or steel prop on a plank or brick base, never loose soil that softens when water spills. Wedges tight, bracing tied both ways.
Tied to the bars, ends taped shut so concrete can't get in. Wiring cannot be added inside a slab later. See conduit before casting.
Conduit · fan box · round boxesFor the toilet stack, the down-line and rainwater, so nobody drills the new roof. See pipe sleeves in the slab.
uPVC pipe · Prince · AshirvadMark the top of the slab on the edge shuttering all round. If the drawing puts the roof slope in the slab, mark it falling towards the outlets.
Before you pour: send photos of the sariya on WhatsApp before dhalai and we'll check them with you. Once the steel is tied, photograph the mesh, the cover blocks and the props. It is a second pair of eyes, not a structural design: your engineer's drawing still decides.
Send steel photosTwo days gives time to count and cover everything, without cement sitting long on a damp site. Material that arrives on the morning of the pour never gets checked.
Sand during the rains: Bihar's sand mining stops in the monsoon months, so balu gets scarce and dear. If your dhalai falls between June and October, buy and cover the balu early. Season advice: dhalai in the monsoon · dhalai in May–June heat.
The pour starts at the far corner and works back towards the stairs, so nobody walks on fresh concrete and the last strip is the nearest one.
| Job on the day | What that person does |
|---|---|
| Mixer feeders | Cement, balu, gitti and the measured water, batch after batch |
| Carriers | Concrete from the mixer to the roof, by tasla or hoist |
| Placers | Tip concrete close to where it goes, never from a height |
| Vibrator operator | Follows the placers and vibrates every part |
| Finishers | Level the top and keep the slope to the outlets |
| Steel watcher | Lifts back bars and cover blocks pressed down by feet |
| Props watcher | Stays under the shuttering, watches props and plates, calls a stop |
| Water person | Keeps drums full and stays at the mixer |
Each picture shows the mistake on the left (in red) and the roof a year or a monsoon later on the right. All six are cheap to prevent and expensive to repair.
With no concrete under them, the bars take in damp, rust and swell, and the ceiling cracks along each bar. Cover blocks of the drawing's size, under every part of the mesh.
Water spilt on the day softens the ground, the prop sinks, and the slab sets with a sag. Every prop on a plank or bricks, wedges tight, braced both ways.
The extra water leaves tiny holes as it dries out. Fix the water per bag before the day (no more than 25 litres) and use one marked bucket.
Hand tamping leaves air around the bars. The honeycomb lets water reach the steel. Book a needle vibrator with a spare needle, and vibrate every strip.
New concrete does not bond well to concrete that has already set: a cold joint. Spare bags, stored water and a spare needle remove the usual reasons for a stop.
The heavy gitti lands first and the paste splashes away, so that spot has stones with nothing between them. Tip the tasla close to the surface.
The job is not over when the last tasla goes up. The next two weeks decide how strong the roof gets.
Curing means keeping the slab wet so the cement keeps gaining strength. Start the next morning, once the surface takes water without the paste washing off. Make small mud or mortar bunds and keep water standing in them. Sprinkling twice a day is not curing: the slab must never dry out in between.
IS 456 asks for at least 10 days with blended cement and 14 in hot, dry weather. All our UltraTech bags (PPC, Super, Weather Plus) are blended, so 10 days is the floor. Full method: curing after dhalai.
The shuttering contractor wants his plates back. Let him take side forms early, but the props under the slab and beams stay for the days in the chart. A slab that sags from early stripping cannot be fixed. Details for slab, beam and chhajja: when to remove shuttering.
Fine surface cracks in the first days usually mean the top dried too fast. Keep curing; tell us what you see. Cracks right through, or along bars, need your engineer. More: cracks after dhalai.
Put in the roof size and the dhalai date. You get the cement, balu, gitti, WP+200 and water for a plain slab, and the dates for each check. Steel comes from your drawing.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Balu—Clean, coarse, no mud. Wet balu bulks: measure it dry, or ask us.Ask today's rateFor a plain slab of even thickness. Beams under the slab add concrete: add them in the full calculator. The working is in how many bags for a slab. Cutting and delivery are charged separately; ask for the amount for your site (delivery).
Cover blocks, tarpaulin and anything else not on this list: we can order it for you; ask on WhatsApp for the time it takes. Today's prices: cement · sariya · balu and gitti. Ready-made order for your slab: slab-day kit.
| 1 week before: steel and shuttering | |
|---|---|
| Sariya size, spacing, top bars, laps and chhajja bars as per drawing | |
| Cover blocks under the bottom bars everywhereusual slab cover 20 mm; no bricks or stones | |
| Chairs holding the top bars at height | |
| Plates level, joints sealed, swept clean, oiled | |
| Props on planks or bricks, wedges tight, braced both ways | |
| Conduits and fan boxes tied, ends taped | |
| Pipe sleeves and roof outlets placed | |
| Slab thickness (and slope, if in the slab) marked on the edge | |
| Steel photos sent on WhatsApp for a check | |
| 2 days before: material, water, machines, people | |
| Cement counted, on planks, covered, packing date checked, 2–3 spare bags | |
| Balu and gitti delivered and covered | |
| WP+200 on site, if usedbags × 0.2 litre | |
| Water stored in drums or tank; one marked bucket for mixing water | |
| Mixer, vibrator, spare needle and fuel booked by date and time | |
| Labour named for every job, including the props watcher | |
| Forecast checked, tarpaulin and lights ready | |
| Dhalai day | |
| Start at first light | |
| Same mix and water in every batchno more than 25 litres per bag | |
| Tipped close, never dropped from height; every part vibrated | |
| One direction, from the far end, no halt | |
| Someone under the shuttering the whole time | |
| Top levelled, slope kept, covered once stiff if sun or wind are strong | |
| After | |
| Curing from next morning: 10 days minimum, 14 if hot and dry | |
| Slab props in for 14 days; beam props 14 to 21 | |
| No bricks or bags stacked on the roof while props are in | |
Figures: IS 456:2000 (cover, water-cement ratio, curing, props) and UltraTech (WP+200 dose). Your engineer's drawing and instructions come first.
A week before: sariya size, spacing and laps as per the drawing, cover blocks under the bottom bars, chairs under the top bars, level and sealed shuttering, props on a firm base, conduits, fan boxes and pipe sleeves. Two days before: cement, balu and gitti on site and covered, water stored, mixer and vibrator booked with a spare needle, labour named for every job, and the forecast checked. The printable list runs in that order.
About two days before: time to count, cover and check the cement, balu and gitti, without the cement sitting long on a damp site. The steel should be tied and checked a week before, so there is time to correct it.
No more than about 25 litres per 50 kg bag, a water-cement ratio of 0.5 (standard figure, IS 456). Wet balu already carries water, so use less. Agree the amount with the mason before the day and measure it with one marked bucket.
Yes. A mixer keeps every batch the same, and a needle vibrator removes trapped air that hand tamping leaves behind. The thekedar or shuttering contractor usually brings them or hires them for the day. Book both by date and time, with a spare needle and fuel. More in mixer and vibrator for dhalai.
At first light, so the top is finished before the sun is high. Wet the shuttering and keep the gitti in shade before you start. Full advice: dhalai in May–June heat.
Start the next morning and keep the slab wet without a break. IS 456 asks for at least 10 days with blended cement such as PPC, which is what most bags in Bihar are, and 14 days in hot, dry weather. OPC needs at least 7. See curing after dhalai.
It is optional, and it helps a roof that will face the rain. The dose is 200 ml per 50 kg bag: mix the dry material with half the water, add WP+200 to the other half, then combine (UltraTech). A 100-bag slab needs 20 litres. It does not replace good compaction and curing. See waterproofing in the dhalai.
Avoid it. A stop leaves a cold joint, a weak line that often seeps later. Spare cement, stored water and a spare vibrator needle remove the usual reasons. If a stop cannot be avoided, ask your engineer beforehand where the joint may go. If it already happened: when the dhalai stops midway.