Pipe holes in the slab before dhalai: sleeves for the 110 mm stack, the down-line and the floor traps, so nothing is drilled later
Every pipe that will ever cross the slab needs a hole cast into it on dhalai day. The hole is made with a sleeve: a short piece of SWR pipe, one size bigger than the pipe it will carry, tied to the steel and capped before the concrete comes.
- 1Toilet stack, 110 mm: a 160 mm sleeve, for each stack, in every slab it passes, roof included (it must vent above the roof).
- 2Tank down-line and pump line: a 75 mm sleeve each, in every slab between the pump and the tank and the taps.
- 3Upstairs bathroom: a sunken slab, 250–450 mm deep, so the traps sit in the floor. Without a sunk, a sleeve under the WC, the floor trap and the basin.
- 4Geyser or solar line, balcony or kitchen drain, rain outlets: one each, where they cross.
Choose the WC and fix the bathroom layout before the shuttering goes up. That decides where every hole goes.
Which holes your slab needs
Walk the house in your head, floor by floor, and ask of every pipe: does it cross this slab? If yes, it needs a sleeve in it, and the place is fixed by the walls and fittings above and below. Most houses in Muzaffarpur have the same handful.
Sunken bathroom or flat slab?
An upstairs bathroom is either cast sunken (the slab under it drops 250–450 mm, the traps and drains lie in that box and are filled over), or cast flat with every drain going straight down through the slab and running under the ceiling of the room below. The choice is made now and cannot be changed after dhalai.
With a sunk, the floor of the box gets no holes at all: that is the point of it. The only sleeves are where the drain leaves the box for the stack (D in the drawing), or the stack itself if it rises inside the bathroom. With a flat slab you need a sleeve under the WC outlet, the floor trap and the basin waste, and the pipes show in the room below unless it gets a false ceiling. On our sites the sunk is the usual choice for a house; a flat slab suits a bathroom over a store or a staircase.
Where the stack goes
Keep the 110 mm stack on an outside wall or in a shaft, never through a bedroom. If the ground-floor toilet comes now and the upper one later, put the upper bathroom right over the lower one so one stack serves both: two toilets on one line. Then the first-floor slab needs only the one stack sleeve, and the roof slab one more for the vent.
The lines people forget
The pump line from the boring or sump up to the roof tank crosses every slab. So does a geyser or solar line fed from the roof. A washing-machine or kitchen drain upstairs, and the rain outlets through the parapet, are the others. The rain outlet goes at the lowest point of the roof slope, as on the chhat dhalai checklist.
How big each sleeve should be
Rule: the sleeve's bore should be at least 25 mm more than the pipe's outside, so there is about 12 mm or more all round to push mortar in later (usual practice). Use a piece of SWR pipe as the sleeve; it is cheap, round and does not rot.
| Pipe that will pass | Sleeve | Gap all round |
|---|---|---|
| 110 mm toilet stack or WC drain | 160 mm SWRbore about 151 mm | about 20 mm |
| 75 mm floor-trap or washing-machine drain | 110 mm SWRbore about 103 mm | about 14 mm |
| ½″, ¾″, 1″, 1¼″ supplydown-line, pump line, geyser line | 75 mm SWRbore about 70 mm | 14–24 mm |
| 1½″ or 2″ supply | 110 mm SWR | 21–27 mm |
| 40 mm basin waste (flat slab) | 75 mm SWR | about 15 mm |
Bores worked out from the makers' wall thickness: a 160 mm SWR pipe has a 4.0–4.6 mm wall (Type B) and a 110 mm one 3.2–3.8 mm. The supply pipe sizes are Prince Easyfit's outsides: 1″ is 33.4 mm and 1½″ is 48.3 mm. A 50 mm sleeve round a 1″ line leaves only about 6 mm, too thin to pack, so we don't use it for supply lines.
Length of each piece: slab thickness plus about 50 mm standing above the top, so about 200 mm for a usual 125–150 mm slab (usual practice). Five or six sleeves come out of one short offcut.
How deep to sink the bathroom slab
The sunk must be deep enough for the deepest trap plus the fall of its drain to the outlet, plus the screed on top. 250–450 mm covers most houses (usual practice). A western WC with its S-trap built in needs the least; an Orissa pan sitting on its P-trap needs the most. Which WC is the first thing to decide: Orissa pan or western, then S-trap or P-trap.
| Add up | How to get it |
|---|---|
| Trap height | From the slab to the centre of the trap outlet, measured on the pan, trap and floor trap you will buy. Bring them to site or ask us for the piece. |
| Fall of the drain | 1 in 60 over the run from the farthest trap to the outlet: 20 mm for 1.2 m, 40 mm for 2.4 m, 50 mm for 3 m. |
| Screed and tile | About 40 mm over the highest pipe (usual practice; Birla White asks at least 20 mm of screed over a pipe). |
Example: a trap outlet 200 mm up, a 2.4 m run (40 mm fall) and 40 mm screed come to 280 mm, so the engineer casts a 300 mm sunk. The engineer sets the slab and beam steel for the drop; the sunk's side, where the drain leaves, gets sleeve D at the drain's level.
Waterproofing of the sunk, the 48-hour water test and the filling come later and are on bathroom waterproofing; the WP+200 for the slab concrete is on waterproofing at dhalai.
Fixing a sleeve so the concrete can't move it
- Mark from two walls. Measure each centre from two wall lines below (not from the shuttering edge) and chalk a cross on the plate. For a stack, keep the centre about 100–125 mm off the bare brick face so the pipe clears plaster and a clamp (usual practice).
- Fix a stop on the plate. Nail a round wooden disc or a ring of short nails just inside the sleeve's bore, so its bottom can't slide.
- Fit between the bars. Slab bars are often closer than a 160 mm sleeve, so one bar may have to be eased aside to the sleeve's edge. Never cut a bar. If one must be cut or moved far, your engineer says what extra steel goes round the hole.
- Tie it plumb. Binding wire in an X from the sleeve to the bars on all four sides; check it stands straight with a level.
- Cap it. Tape over the top, or stuff it with wet sand and tape, so slurry can't fill it.
- Mark it on the plan and photograph it with a tape in the picture, before the concrete comes.
The check, with the plan in one hand and a tape in the other
Look up from below: every sleeve should show a clean round mouth. Poke out any slurry from the top the same week, while it is still soft. Leave the tape on top until the plumber comes.
The rest of slab day (steel, cover, props, curing): chhat dhalai checklist · cement for it: cement for chhat dhalai · the plumbing checks after this one: plumbing checklist by stage
The four sleeve mistakes, and what to do if a hole was missed
1 · A hole broken out later
A hammer and chisel cut the slab steel, crack the concrete round the hole and leave a ragged gap that never seals as well. Most round stains on a ceiling under a bathroom start at a pipe that crossed the slab like this.
2 · A sleeve through a beam
A beam carries the slab; a hole in it is your engineer's decision, not the plumber's. Move the sleeve beside the beam, or let the engineer decide.
3 · No cap
An open sleeve fills with slurry and becomes a plug of concrete inside a plastic ring. Cap every one and check from below when the shuttering comes off.
4 · Not tied
Wet concrete pushes a loose sleeve over. A leaning sleeve means a bent stack or a pipe that rubs on one side, which cannot be packed.
If a hole was missed
Don't let anyone break it. Ask your engineer to mark where the bars and beams are, then have it cut with a diamond core-cutting machine at the size in the table above. The core gives a clean round hole that is packed and sealed the same way as a sleeve. It costs a visit and a day; a hammered hole can cost the ceiling below.
Sealing the sleeves later
The gap round each pipe is packed solid with SBR mortar when the plumbing is done, and the waterproof coat is carried up the pipe. That is step 3 on bathroom waterproofing; it is not repeated here.
Electrical on the same slab
Conduit, fan boxes and round boxes go on the same shuttering the same day, and a slab cast without them cannot be wired later either. Keep the conduits clear of the plumbing sleeves. The electrical list is on conduit before slab casting.
Sleeve list maker
Answer for the slab you are casting next. It lists the sleeves with sizes and writes the message to us.
What to buy before dhalai
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
110 mm SWR pipeThe stack, and sleeves for 75 mm drainsAsk today's rateper length 160 mm and 75 mm SWR piecesSleeves for the stack and supply lines · we can order it; ask on WhatsApp for the time it takesAsk today's rateper length Easyfit UPVC pipeDown-line and pump lineAsk today's rateper length UltraTech Weather Pro WP+200In the slab concrete, 200 ml per bagAsk today's rateper pack UltraTech Seal & Dry SBRPacking the sleeves laterAsk today's rateper 1 kg P-trap 125×110For an Orissa pan; decides the sunk depth₹ 223per pieceCutting and delivery are charged separately; ask for the amount for your site. Delivery · today's pipe rates
What people ask before dhalai
What size sleeve for a 110 mm toilet pipe? (latrine pipe ke liye sleeve)
A 160 mm SWR pipe piece. Its bore is about 151 mm, so a 110 mm stack has about 20 mm all round to pack with mortar later. A piece that hugs the pipe leaves a gap too thin to fill.
Why a sleeve, not the pipe cast straight in?
A sleeve gives a clean hole of the right size in the right place. The pipe can be lined up with the walls built later, changed one day, and the gap packed solid. A pipe cast straight in is often off line by the time the walls go up, and the plastic-to-concrete joint opens as the slab moves with heat.
Can the hole be drilled after the slab is cast?
Only with a diamond core-cutting machine, after your engineer marks the bars and beams. Never with a hammer and chisel.
How deep should the sunken bathroom slab be?
Usually 250–450 mm (usual practice). Add the trap height of the pieces you will buy, the drain's fall at 1 in 60 over its run, and about 40 mm of screed. A western WC needs the least, an Orissa pan with its P-trap the most.
Do I need sleeves on the ground floor too?
Not in a slab, but in the plinth: where the toilet drain goes out to the chamber or septic tank, and where the water and pump lines come in. Your engineer decides whether a plinth beam can take the hole.
Will you come to the site to check?
We don't promise site visits. Send photos of the shuttering on WhatsApp the day before dhalai, with a tape in the picture, and we will look at the sleeves with you.
Twenty years on sites around Muzaffarpur. He walks the shuttering with the plumber the evening before every dhalai. Pipe and sleeve sizes on this page were checked on 14 Nov 2026 against the makers' tables named below; where a figure is site practice, the page says so. The slab steel, beams and the sunk drop are always your engineer's call.
Where the figures come from
- Finolex Pipes, SWR brochure and maker SWR catalogues to IS 13592: 110 mm pipe wall 2.2–2.7 mm (Type A), 3.2–3.8 mm (Type B); 160 mm wall 3.2–3.8 mm (Type A), 4.0–4.6 mm (Type B). Bores on this page are worked out from these.
- Prince Easyfit UPVC, made to ASTM D1785, as on our Easyfit Sch 40 and Sch 80 page: 1″ = 33.4 mm and 1½″ = 48.3 mm outside.
- Studio Matrx, Bathroom planning for new homes in India: sleeves for the stack and floor traps are cast in at slab casting; sunken slab 250–450 mm. It agrees with our site practice.
- Birla White, as set out on our bathroom waterproofing page: at least 20 mm screed over pipes; sleeve packing and the water test.
- Drain fall 1 in 60, as on our plumbing checklist (IS 1742 is reported to give 1 in 57 for a 100 mm drain).
- Sleeve gap of 12 mm or more, the 50 mm stand-up, 200 mm pieces, stack 100–125 mm off the brick, disc-and-wire fixing, sunk depth range: usual practice on Muzaffarpur sites.