Plumbing checklist for a new house: what to check before the slab, before plaster, before tiles, and at the end

The short answer
  1. 1Before the slab is cast: a sleeve wherever a pipe will cross it, and the sunken bathroom floor.
  2. 2Before plaster: every supply pipe pressure tested, every drain laid with its fall.
  3. 3Before tiles: traps set, the sunken floor coated and held under water for 48 hours.
  4. 4After paint: taps and WCs fitted, flushed, and the whole house left overnight with the tank marked.

Each stage buries the pipes of the one before: concrete, then plaster, then tiles. A leak found after tiling means breaking tiles to reach a pipe that cost a few hundred rupees. So every test happens while the pipe can still be seen.

6 kg/cm²
Pressure test, 1 hourWater only, after 24 h cure. IS 2065 asks for at least 1.5× working pressure.
1 in 60
Fall of a 110 mm drainOne inch for every five feet of pipe, towards the chamber.
50 mm · 48 h
Bathroom water testOn the coated sunken floor, outlets plugged (Birla White).
One house, four checks
A two-storey house cut open, with the four plumbing checks marked Section of a ground-plus-one house. A tank on the roof feeds a blue supply line down through a sleeve in the roof slab to the taps. A grey 110 mm drain stack runs from a vent above the roof, through sleeves in both slabs, to an inspection chamber outside, with a fall under the floor. Marker 1 at the sleeves, marker 2 at a pressure gauge on the upstairs bathroom wall, marker 3 at the sunken bathroom floor holding water, marker 4 at the tank and the taps. ROOF SLAB FIRST-FLOOR SLAB sunken floor to the chamber, falling Sleeves in the slabat every crossing Pressure test,drain falls Water test48 h in the sunk Taps, WC,tank test GROUND FLOOR 1 2 3 4
Not to scale. Blue is the supply from the tank, grey is the 110 mm drain stack, yellow marks a sleeve, red is the waterproof coat in the sunken floor.
1
Check 1 of 4

Before the slab is cast

Do it the day before dhalai, for every slab. What closes it: concrete.
0 of 8
The one mistake at this stage

"The plumber will cut a hole later." A hole hammered or cored through a new slab cuts its steel, cracks the concrete round it, and never seals as well as a cast sleeve. Most round stains on a ceiling below a bathroom start at a pipe that crossed the slab without one.

The rest of slab day (steel, cover, shuttering, curing): chhat dhalai checklist · the waterproofing that goes into the slab concrete: waterproofing at dhalai

One bathroom slab, from above
Sleeves on an upstairs bathroom slab before casting Top view of the shuttering and steel for a bathroom and the room beside it. A sunken area is marked for the bathroom. Yellow circles show sleeves: a large 160 mm sleeve for the 110 mm stack in the corner, a 75 mm sleeve for the tank down-line, a sleeve under the WC position, and a rain outlet on the roof edge. A small section shows a sleeve standing above the slab top, tied to the bars, with a cap. SUNKEN BATHROOM down-line stack: 160 mm sleeve WC drain trap rain outlet roof outlet Sleeve in section one size above the pipe top above the slab capped, tied to steel
Usual practice drawn for one upstairs bathroom. Sleeve sizes and heights are site practice, not a maker's rule; the slab steel and beams are your engineer's call.
2
Check 2 of 4

Before plaster

Do it after the pipes are in and before the plaster mason starts. What closes it: plaster.
0 of 10
The one mistake at this stage

Plastering first and "opening the tap to see". A tap at tank pressure pushes about 1 kg/cm²; a joint that holds that can still weep at the pump's 3 or 4. Only a gauge held for an hour finds the half-glued joint, and plaster over an untested line is how a new wall gets cut open.

A joint that weeps on the test: leaking pipe joint · how a solvent joint should be made: Prince's seven steps

The pressure test on one bathroom wall
Pressure testing a bathroom's concealed pipes before plaster A brick wall with pipes in vertical chases leading to four outlets, each closed with a red plug. A hand test pump with a gauge is connected at the bottom; the gauge needle points to 6 kg/cm². At the highest outlet, a note says let the air out here first. Below, a drain pipe falls from left to right with a note: one inch of fall for every five feet. 6 from the tank side,let the air out first plugs on every outlet Test pump + gauge: 6 kg/cm², 1 hour. Needle moved? Find the wet joint, cut it out, test again. 110 mm drain: 1 inch fall every 5 ft (about 1 in 60)
Test pressure and time: IS 2065 and Prince's CPVC manual (water only, one hour). 6 kg/cm² is 1.5 times a house pump's 4. The fall is drawn steeper than real.
3
Check 3 of 4

Before tiles

Do it before the sunk is filled, and again before the first tile. What closes it: filling, screed and tiles.
0 of 8
The one mistake at this stage

Filling the sunk the same day it was coated "because the tiler is waiting". The 48-hour test is the only time the coat can be seen and fixed. After the brickbat and tiles go on, a wet ceiling below means taking up the whole floor.

Water from an old bathroom already reaching the room below: bathroom water in the room below · tiles and adhesive for the bathroom: cement or adhesive

The sunken floor under water
The 48-hour water test in a sunken bathroom floor Section of a sunken bathroom slab with a red waterproof coat on the floor, the corner golas and up the side walls. Blue water 50 mm deep stands on it. The floor trap is plugged with a bag of sand, a pipe sleeve is packed, a chalk line marks the water level on the wall, and a small ridge holds the water at the door. Below the slab, an eye checks the ceiling. A second small drawing shows the screed falling to the trap. chalk line at the water level sleeve packed trap plugged door ridge 50 mm of water · 48 hours ceiling below checked twice a day screed 1 in 100
Not to scale: the coat is far thinner than drawn. 50 mm for 48 hours is Birla White's test; the sand-bag plug and door ridge are usual practice.
4
Check 4 of 4

Final, before the last payment

Do it after the taps, WCs and basins are fitted. What closes it: the plumber's last bill.
0 of 9
The one mistake at this stage

Paying in full the day the taps are fitted. The overnight tank test costs nothing and takes one night. Hold the last payment until it passes, and until every bathroom has been used for a day.

A wet patch that shows up later: where is the water coming from · weak water upstairs: low water pressure

Valves labelled, tank marked
Where the valves are and how the overnight tank test is marked A roof tank with a stick standing in it and a pencil mark at the water line; a ball valve right after the tank labelled whole house. The down-line goes to three branches, each with a stop cock labelled: upstairs bathroom, downstairs bathroom, kitchen. A moon and a sun show: mark at night, check at dawn. mark at bedtime,check at dawn WHOLE HOUSE BATHROOM · UPSTAIRS BATHROOM · DOWNSTAIRS KITCHEN Label written on the wall or a tag beside each valve.
Usual practice. If the mark falls overnight, shut all but one stop cock the next night: the branch that drops is the leaking one.

Send us what's still open

We'll look at the unticked items with you, and send the material for the next stage with today's price. A photo of the gauge or the wall helps.

Send to Arun
0/8Before slab
0/10Before plaster
0/8Before tiles
0/9Final

Your ticks stay on this phone only. Nothing is sent until you press the button.

The material list, by stage

What to buy, and when to buy it

Buy each stage's material a few days before that stage. Pipes left in the sun for months go brittle, and a WC bought before the slab may not match the hole. Every item below can be ordered; anything not on the shelf, we order for you: ask on WhatsApp for the time it takes.

BeforeBuyFrom us
1 · SlabSleeves for the stack and down-lines, roof outlets, waterproofing for the slab concreteChoose the WC now, so its hole is rightSWR pipe · UPVC pipe · WP+200
2 · PlasterUPVC pipe and Sch 80 fittings, CPVC for the geyser line, ball valve, MTA/FTA, brass-insert elbows, end caps, solvent cement, Teflon tape, 110 mm drain pipe and bendsPlugs for every outlet before the testEasyfit · CPVC · fittings · ball valve · solvent
3 · TilesP-trap and floor trap, SBR for sleeves and gola, the waterproof coat, tile adhesive and groutThe pan goes in with its trap, before the tilesP-trap · Seal & Dry SBR · Hi-Flex · TileStix
4 · FinalWCs and pans, angle valves, connection pipes, Teflon tapeBring the WC's pipe measurementCERA Cinco 300 · Chanel 220 · Calina pan
Questions people ask us

Short answers

When should plumbing be done in a new house? (plumbing kab karwayein)

In four steps that follow the building. Sleeves and the sunken bathroom floor are fixed at slab casting. Supply and drain pipes go in after brickwork and are pressure tested before plaster. Traps, the sunken floor coat and its water test come before tiles. Taps, WCs and the final tests come last, after paint.

What pressure should a house plumbing line be tested at?

IS 2065 asks for 1.5 times the highest working pressure and not less than about 5 kg/cm². A house pump pushes 3 to 4 kg/cm² against a closed tap, so we test at 6 kg/cm² with water only, after the joints have cured for 24 hours, and hold it for one hour (Prince's CPVC manual). The needle must not move. If a concealed valve's box gives a lower test figure, test at that.

How long should the bathroom water test be?

50 mm of water on the coated sunken floor for 48 hours, outlets plugged, with the ceiling below checked twice a day (Birla White). It is done on the bare slab and again on the waterproof coat, before the sunk is filled. The full sequence is on bathroom waterproofing.

What slope should a drain pipe have?

For a 110 mm drain, about 1 in 60: one inch of fall for every five feet of pipe. IS 1742 is reported to give 1 in 57 for a 100 mm building drain. A bathroom floor falls about 1 in 100 to its trap.

Can the pressure test be done with air?

No. Prince's manuals for both CPVC and UPVC say water only, never air or gas. Trapped air is dangerous under pressure, so the line is filled slowly and the air let out at the highest point first.

Why a sleeve, and not just the pipe in the concrete?

A sleeve leaves a clean hole the pipe can pass through, be changed through, and be packed tight with SBR mortar. A pipe cast straight in, or a hole broken later, leaves a crack round it where water creeps down to the ceiling below.

Will you come to the site to check?

We don't promise site visits. Send photos on WhatsApp before dhalai, before plaster and before tiles, with the gauge in the picture for the pressure test, and we will look at them with you.

Arun Tiwari
Thekedar · site work, costs and plumbing, Tashya Ventures

Twenty years on sites around Muzaffarpur. This is the list he walks with the plumber at each stage, checked on 13 Nov 2026 against Prince's CPVC and UPVC manuals and the IS codes named below. Where a figure is site practice rather than a maker's rule, the page says so.

Where the figures come from

  1. Prince Pipes, FlowGuard Plus CPVC technical manual: test with water only, never air; fill slowly and vent air at high points; test before concealed work, not before 24 hours of curing; up to one hour is sufficient; mind the lowest-rated part (valves, unions, threads).
  2. Prince Pipes, Easyfit iN UPVC technical manual: water only; vents at high points; test pressure 1.5 times the lowest-rated part, held half an hour; joint cure-time table. Where the two manuals differ, we take the longer time.
  3. IS 2065, Code of practice for water supply in buildings, cl. 14.2 as summarised by InfraLens: hydraulic test at 1.5 times the maximum working pressure, not less than 0.5 N/mm² (about 5 kg/cm²).
  4. IS 1742, Code of practice for building drainage, as reported by InfraLens: minimum gradient 1 in 57 for a 100 mm drain. We round to 1 in 60 for a 110 mm line.
  5. Birla White and UltraTech sheets, as set out on our bathroom waterproofing page: 50 mm water for 48 hours, two coats, gola, SBR packing.
  6. Sleeve sizes, sunk depth, pipe sizes, bucket and drain tests, valve labels: usual practice on Muzaffarpur sites, labelled as such on the page.

Send us your bathroom plan

Arun will mark the sleeves, the pipe sizes and the traps, and send the list for your next stage with today's price on WhatsApp.