Column size for a house: 9×9, 9×12 or 12×12, how many bars, and how many floors
Abhishek Ranjan, Diploma Civil Engineer · checked against IS 456, IS 13920 and the IIT Kanpur–BMTPC tips, 13 Nov 2026
The short answer
House
Often built on Bihar sites
What a Zone IV drawing usually starts from
G
9 × 9 in4 bars of 12 mm
9 × 12 to 12 × 12 in12 × 12 if a floor may come later4 × 12 mm passes only in 9 × 9
G+1
9 × 12 in6 bars of 12 mm
12 × 12 in4 × 16 mm, or 8 × 12 mm
G+2
12 × 12 in4 × 16 + 2 × 12 mm
12 × 12 to 12 × 15 inmore steel in the ground-floor columns
Muzaffarpur is in earthquake Zone IV. The earthquake detailing code, IS 13920, asks for columns at least 300 mm (12 in) wide, and IS 456 asks for steel of at least 0.8% of the column. Those two minimums decide most of the right-hand column. The rest is load: corner, side and middle columns differ, and only a calculation shows by how much.
300 mm
Narrow side, Zone IVAbout 12 inches. IS 13920:2016.
0.8%
Least steelOf the column's area. 4 × 12 mm fails in 12 × 12.
4 × 12
Fewest bars4 bars, none thinner than 12 mm. IS 456.
Your engineer or architect decides the column size and bars. This page shows the usual ranges and the code's minimums, so you can read your drawing, check the cage on site and order the right sariya. It is not a design. No drawing yet? We work with Ar. Sumit Kumar, whose house design set includes the structure sheet with every column marked.
Three usual columns, drawn to scale
To scale (1 mm = 0.6 px). Bar counts are the common site versions, not a design. Percent = steel area ÷ column area; IS 456 asks for at least 0.8%. Cover: IS 456, 26.4.2.1.
Size by floors
What sites build, what the Zone IV code asks, and why they differ
Online tables give one size per floor count. Ours gives two, because in Muzaffarpur the gap between them is the real question at the counter.
Ground floor only (G)
Small house, flat roof, no floor planned above
9 × 9 in4 × 12 mm8 mm rings
The common village and town column. Four 12 mm bars are 0.86% of it, so it just passes the steel minimum.
IS 13920's 1993 edition let a column drop to 200 mm only when it is under 4 m tall and the beams are under 5 m long. The 2016 edition asks 300 mm. That old allowance is why 9-inch columns are still drawn.
If even one floor may come later, this is not your column. See upper floor later.
Two floors (G+1)
The most common new house in our area
12 × 12 in4 × 16 mmor 8 × 12 mm
Sites often build 9 × 12 with six 12 mm bars, so the column hides inside a 9-inch wall.
For Zone IV the code width is 300 mm, so the drawing usually goes to 12 × 12, and the column shows on one face of the wall.
At 12 × 12, four 12 mm bars are not enough (0.5%). Four 16 mm or eight 12 mm are the usual answers.
Three floors (G+2)
Rooms to let, or a shop below and home above
12 × 12 to 12 × 15 in4 × 16 + 4 × 12 mm
Ground-floor columns carry three floors, so they get the most steel. Corner and middle columns can differ.
A 12 × 15 column needs at least 912 sq mm of steel: four 16 mm bars alone (804) fall short.
Shops on bare columns with rooms above need a full engineer's design; the reason is on our Zone IV page.
What moves the size up
Ask your engineer about these
Long rooms: columns more than about 4 m (13 ft) apart carry more.
Beams with 16 mm bars: IS 13920 wants the column at least 20 times the beam bar, so 320 mm, a little over 12 in.
Soft or filled soil, a water tank on the roof, a shop floor, or a plot in the north-east blocks where Zone V is close.
Long, flat columns (9 × 24, 9 × 30) are weak sideways. IS 13920 prefers the short side to be at least 0.45 of the long side.
The check anyone can do
The 0.8% check: does your bar count fit your column?
IS 456 asks that the bars in a column add up to at least 0.8% of its area. It takes one multiplication, and it catches the commonest mistake: a bigger column with the same four 12 mm bars.
Column
Bars
Steel
Against 0.8%
9 × 9 in (230 × 230 mm) · needs 423 sq mm
9 × 9
4 × 12 mm
0.86%
Passes
9 × 12 in (230 × 300 mm) · needs 552 sq mm
9 × 12
4 × 12 mm
0.66%
Too little
9 × 12
6 × 12 mm
0.98%
Passes
12 × 12 in (300 × 300 mm) · needs 720 sq mm
12 × 12
4 × 12 mm
0.50%
Too little
12 × 12
6 × 12 mm
0.75%
Too little
12 × 12
4 × 16 mm
0.89%
Passes
12 × 12
8 × 12 mm
1.01%
Passes
12 × 12
4 × 16 + 4 × 12
1.40%
Passes
12 × 15 in (300 × 380 mm) · needs 912 sq mm
12 × 15
4 × 16 mm
0.71%
Too little
12 × 15
4 × 16 + 2 × 12
0.90%
Passes
12 × 15
6 × 16 mm
1.06%
Passes
The red line in each bar is 0.8%. The bar runs to 2%. Passing the minimum does not make a column right for your load; it only rules out the ones that cannot be.
Column area in sq mm
Multiply the two sides in mm. 9 in = 230 mm, 12 in = 300 mm, 15 in = 380 mm. A 12 × 12 column: 300 × 300 = 90,000.
The least steel
0.8% of that: 90,000 × 0.008 = 720 sq mm.
Add up the bars
One 12 mm bar is 113 sq mm, one 16 mm bar is 201. Four 16 mm = 804. Eight 12 mm = 905.
Compare
804 and 905 are above 720, so either passes. Four 12 mm (452) does not.
The upper limit is 6% (4% is the usual working limit, because laps double the steel at the joint). House columns are nowhere near it. Bar sizes and kg per metre: sariya weight per metre.
Code minimums you can see on the cage
Six things to check before the column is shuttered
These are the outer limits from IS 456 and IS 13920, not a design. A cage that breaks one of them needs a call to your engineer before the concrete goes in.
1Bars: 4 or more, 12 mm or thicker
One in every corner of a rectangular column; a round column needs 6. No main bar thinner than 12 mm (IS 456, 26.5.3.1). Bars along a face no more than 300 mm apart.
2Rings: 8 mm, closed, 135° hooks
IS 456 allows 6 mm rings for small bars, but IS 13920:2016 asks at least 8 mm in Zone IV. Hooks bent back into the core, ends at least 10 times the ring bar (80 mm for 8 mm). Ring rules near joints, in detail: Zone IV page.
3Ring spacing in two zones
Near every floor and beam: 75 mm (3 in), for at least 450 mm. In the middle: half the narrow side, 115 mm for a 9-inch column, 150 mm for 12-inch. Rings continue through the joint. Count them for your house with the ring calculator.
4Laps in the middle half only
About 50 times the bar: 600 mm for 12 mm, 800 mm for 16 mm. Only half the bars joined at one level. Rings over the lap no more than 100 mm apart. More: lap length.
540 mm cover all round
IS 456 asks at least 40 mm of concrete outside the main bars of a column. Tie 40 mm cover blocks to the rings on all four faces, every metre or so. Bars touching the shuttering rust out. Why cover matters: cover blocks.
6M20 concrete or better
Both IS 456 and IS 13920 set M20 as the least grade. Columns facing rain are often drawn in M25. Mixes and water: M20 and M25 concrete, at most 25 litres of water per bag.
Extra tie when a ring side passes 300 mm: in a 12 × 15 column the bars are still close enough, but in wider columns IS 13920 asks for a cross-tie across the middle so the face bars cannot buckle. Your drawing shows it if it is needed.
Ground floor now, upper floor later
Can my columns take another floor? Only if they were drawn for it
This is the question behind most column questions at our counter. The answer is settled before the first footing is dug, not when the second floor starts.
Not to scale; one floor squeezed to fit, two of the bars shown. Rules from IS 13920 as set out in IIT Kanpur–BMTPC Earthquake Tip 19; the 100 mm over the lap is the 2016 edition's figure (Tip 19, from the 1993 edition, says 150 mm; we take the closer one).
Why a column for one floor cannot simply carry two
A 9 × 9 column with four 12 mm bars is drawn for the weight of one roof. A second floor roughly doubles what the ground-floor column and its footing carry.
The footing was sized for one floor too. Strengthening it later means digging around a finished house.
In Zone IV the 9-inch column is also below the code width for a two-storey frame.
So if a floor might come in five or ten years, tell your engineer today. The columns and footings are designed for the final house; the extra steel now is far cheaper than jacketing columns later.
What to leave on the roof for the next floor
Column bars sticking out above the roof, at least the lap length: 600 mm for 12 mm bars, 800 mm for 16 mm.
Wrap or coat them against rust, and cap the ends so nobody is hurt. Rusted starter bars get cut off, and then the new column has nothing to join.
The column schedule: one small table that decides your 12 and 16 mm order
Every proper structure sheet has a column layout plan (where each column stands, marked C1, C2…) and a column schedule (what each mark is made of). Here is how to read the shorthand.
An example sheet, drawn by us to show the notation. The numbers are not a design for your house. Some drawings write "T16" or "#16" for a 16 mm bar.
Count the marks
On the column layout plan, count how many C1, C2, C3… there are. Check the NOS column agrees.
Read bars per mark
4-16Ø + 4-12Ø means each C1 takes four 16 mm and four 12 mm bars, every floor.
Note floors and heights
Floor to floor height from the section sheet, and how deep the footing sits below the plinth. Some schedules change the bars floor by floor; read each row.
Put it in the calculator below
It turns marks into kg and 12 m bars of 16, 12 and 8 mm, with laps and rings.
Or send us the sheet
Photo of the schedule and the plan on WhatsApp, and we weigh out exactly that list. If your engineer has made a bar bending schedule (BBS), send that; it is better than any estimate.
Your column order
Column sariya from your schedule: 16, 12 and 8 mm
Put in each column mark from your drawing. The calculator counts the main bars from footing to roof with one lap per floor, and the rings by the Zone IV spacing above.
Your column list
16 mm sariya, main bars—1.58 kg per metre (standard weight)—
12 mm sariya, main bars—0.888 kg per metre (standard weight)—
8 mm sariya, rings—0.395 kg per metre (standard weight)—
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Binding wire—Usual practice: about 1 kg per quintal of sariyaAsk today's rate
Columns only. Footings, beams and slab: sariya calculator · roof slab bar by bar: sariya in a chhat. Billed by weighed kg at today's rate. Cutting and delivery are charged separately; ask for the amount for your site.
What goes wrong
Four column mistakes we see before the concrete goes in
Each is easy to spot while the cage is open and impossible to fix after. Ring and joint mistakes are on the Zone IV page; these are about size and bars.
Bigger column, same four 12 mm bars
You see: a 12-inch column with only corner bars of 12 mm
The size went up to meet the code; the steel did not. Four 12 mm bars are 0.5% of a 12 × 12 column, below the 0.8% minimum. Check the bar count against the drawing, not against the last house.
Bars swapped on site
You see: different sizes in the cage from the schedule
"16 mm hasn't come, use six 12 mm instead." Six 12 mm bars have 16% less steel than four 16 mm. Any change of bar size or count goes back to the engineer before the cage is tied. We keep 12 and 16 mm in stock so nobody has to improvise.
Bars against the shuttering
You see later: brown rust lines, then concrete flaking off the column
Without cover blocks the cage leans on one side of the box. That face gets almost no concrete over the steel, and in our damp the bar rusts and swells. Tie 40 mm cover blocks on all four sides before the shuttering closes.
One-floor columns, two-floor plans
You see later: cracks at the column tops, a footing that settles
Built as a ground-floor house to save money now, with a floor added years later on the same 9 × 9 columns. Tell the engineer the final number of floors on day one; that decides the columns and footings.
Send photos of the column cages on WhatsApp before the shuttering closes, and we will look at the bar count, rings and cover with you. It is a second pair of eyes, not a structural design. The day-of list: dhalai checklist.
20 mm bars, ready-made rings, cover blocks or any other size: we can order it for you; ask on WhatsApp for the time it takes. Weights are the standard weight per metre. Is the bar genuine? Check the marks and the licence. Today's price per kg, quintal and piece: sariya rate. Delivery: delivery.
Questions people ask us
Short answers
What is the standard column size for a house? (ghar ke column ka size)
There is no single standard size. On Bihar sites, 9 × 9 inch columns are common for a ground-floor house, 9 × 12 for G+1 and 12 × 12 for G+2. Muzaffarpur is in earthquake Zone IV, and IS 13920:2016 asks for columns at least 300 mm (about 12 inches) wide, so a Zone IV drawing for G+1 or G+2 usually starts at 12 × 12 inches. The structural engineer's drawing decides.
How many bars in a 9 × 9 column? (column mein kitna sariya)
At least 4 bars of 12 mm, one in each corner. That is IS 456's minimum for a rectangular column, and four 12 mm bars come to 0.86% of a 9 × 9 inch section, just over the 0.8% minimum. It is a single-storey column.
Is a 12 × 12 column with 4 bars of 12 mm enough?
No. Four 12 mm bars are only 0.5% of a 12 × 12 inch column; IS 456 asks for at least 0.8%. A 12 × 12 column needs, for example, four 16 mm bars (0.89%) or eight 12 mm bars (1.0%). Your engineer gives the actual bars.
Can my 9 × 9 columns take another floor later?
Only if the engineer designed them for it. A 9 × 9 inch column with four 12 mm bars is drawn for one floor. If you plan to add a floor, the footings and columns must be designed for the final number of floors before you build, with bars left sticking out at the top for the lap. See ground floor now, upper floor later.
How long should the lap be in a column?
For ordinary house work, IIT Kanpur and BMTPC put it at about 50 times the bar size: 600 mm for 12 mm bars and 800 mm for 16 mm. Laps go only in the middle half of the column height, only half the bars are joined at one level, and rings over the lap stay close. Your drawing's figure comes first. More: lap length.
12 mm or 16 mm for columns?
Both are common. What matters is the total steel area for the column size and that every corner has a bar. Four 16 mm bars and eight 12 mm bars both pass in a 12 × 12 column; the engineer picks by load and by how crowded the joint gets with the beam bars.
Which concrete grade for columns?
At least M20 for reinforced concrete under IS 456, and IS 13920 asks for at least M20 too. Many engineers ask for M25 in columns that face rain. Follow the grade written on your drawing. Mixes: M20 and M25.
Which sariya grade for columns in Muzaffarpur?
A ductile "D" grade suits Zone IV: Fe 500D, Fe 550D or Tata Tiscon 550SD. The drawing's bar count assumes a grade, so a change of grade goes back to the engineer. Why the D matters: Zone IV page.
Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures
Civil engineer at our Rewa Road store, Muzaffarpur, where he works out cement and sariya for houses every day. Every rule on this page was checked on 13 Nov 2026 against IS 456, IS 13920 and the IIT Kanpur–BMTPC earthquake tips. Where the sources differ, the page says so and takes the safer side. The design of your house stays with your engineer or architect.
Where the rules and numbers come from
BIS, IS 456:2000, Plain and reinforced concrete: 26.5.3.1 (columns: at least 0.8% and at most 6% steel, at least 4 bars in a rectangular and 6 in a round column, bars not thinner than 12 mm, not more than 300 mm apart along the face); 26.5.3.2 (ties: at least ¼ of the main bar and 6 mm); 26.4.2.1 (40 mm cover to column bars); Table 5 (M20 least grade for reinforced concrete).
BIS, IS 13920:2016, Ductile design and detailing of RC structures: least column width 300 mm or 20 × the largest beam bar; short side preferably at least 0.45 of the long side; rings at least 8 mm; laps in the middle half with rings at 100 mm; cross-ties where a ring side is over 300 mm; M20 least grade. As summarised by CivilEngineeringWeb; wording checked against code extracts quoted in design-software help pages.
IIT Kanpur–BMTPC, Earthquake Tip 19: columns: 300 mm width (200 mm allowed under IS 13920:1993 only for columns under 4 m with beams under 5 m), 135° hooks with 10 × bar ends, end zones and 75–100 mm spacing, lap about 50 × bar in the middle half, half the bars lapped at a time.
BIS, IS 1893 (Part 1):2016 and BMTPC's Bihar hazard map: Muzaffarpur in Zone IV. Details and sources on our Zone IV page.
Bar areas from the bar size (π × d² ÷ 4); standard weight per metre from IS 1786, as on our weight chart.
Site sizes by floor count: usual practice, as also listed by HouseYog and Comaron (column size guides, read 13 Nov 2026).
Send us your column schedule
Photo of the schedule and the column plan, and we send back the 12, 16 and 8 mm list with today's price on WhatsApp. No drawing yet? Ask us to connect you with Ar. Sumit Kumar.