Which size goes where
| Part | Usual size |
|---|---|
| Rings (stirrups)hold main bars, resist shear | 8 mm |
| Roof slabspreads load across the room | 10, 12 mm |
| Columns, beams, footingswhere the design needs heavier steel | 16, 20 mm + |
That is JSW's published thumb rule for an RCC-framed house. Built-up area means every floor added together, not the plot. Use it to budget. Order from your engineer's bar bending schedule, one stage at a time.
Same rule, 3.5 to 5 kg per sq ft, for each size. JSW's own table runs 500 to 2,500 sq ft; we added 300 and 800 because many houses here are that size.
Two houses of the same size can differ by a tonne and a half. These are the things that move your number, so you know which end to budget for.
Every floor above presses on the columns and footings below, so those get heavier. A single storey sits towards 3.5; G+1 and G+2 move towards 5.
A 16-foot hall needs deeper beams and more slab steel than a 10-foot room. Balconies and chhajjas that hang out also add steel.
Footings get wider on weak ground, as on low-lying plots filled with earth. Your engineer sizes them after seeing the soil.
If you will add a floor in five years, the footings and columns must be built for it now. It costs more steel today and saves breaking things later.
The one saving we never suggest: cutting steel below the drawing. North Bihar is a high earthquake zone, and the rings and bars are what hold a frame together when the ground shakes. Why: earthquake zone and your house · why rings matter.
Most families here build in instalments, so there is no need to buy 4 tonnes on day one. Steel left out through a monsoon rusts, and the rate moves between stages. Here is the 1000 sq ft single-storey house, split the usual way.
| Stage | Order now | 1000 sq ft |
|---|---|---|
| 1 · Neevfootings + plinth beam | Footing mesh, column starter bars, plinth beam bars, ringsStarter bars must be long enough to lap with the column bars: lap length | 875–1,250 kg |
| 2 · Columnsground to roof | Column main bars, 8 mm ringsRings are counted per column from the spacing in the drawing, closer near beams | 700–1,000 kg |
| 3 · Lintelover doors and windows | Band or lintel bars, rings, chhajja barsSome houses cast chhajjas with the roof instead | 350–500 kg |
| 4 · Chhatthe biggest order | Roof beam bars, slab mesh, stair bars, binding wireSlab detail: chhat mein kitna sariya · which mm | 1,575–2,250 kg |
| Total3.5–5 kg × 1000 sq ft | Plus laps and cut pieces, which the bar bending schedule already counts | 3,500–5,000 kg |
Sariya is billed by the kg, but it arrives as 12-metre bars. These two tables let you go from the drawing to pieces to kg.
| Part | Usual size |
|---|---|
| Rings (stirrups)hold main bars, resist shear | 8 mm |
| Roof slabspreads load across the room | 10, 12 mm |
| Columns, beams, footingswhere the design needs heavier steel | 16, 20 mm + |
| Size | kg / m | One bar | Bars in 1 q |
|---|---|---|---|
| 6 mm | 0.222 | 2.66 kg | about 38 |
| 8 mm | 0.395 | 4.74 kg | about 21 |
| 10 mm | 0.617 | 7.40 kg | about 13.5 |
| 12 mm | 0.888 | 10.66 kg | about 9.4 |
| 16 mm | 1.58 | 18.96 kg | about 5.3 |
| 20 mm | 2.47 | 29.64 kg | about 3.4 |
Each one either wastes money or takes strength out of the house. All six are common, and all are easy to avoid.
The rule is per sq ft of built-up area: every covered floor added together. Open space doesn't count; each upper floor does.
Strength goes with the bar's cross-section, which falls faster than the diameter. 8 mm in place of 10 mm, or 10 in place of 12, is not a small saving. It is a weaker slab.
"100 pieces" means nothing without the size. The bill is in kg; ask for the weight and check it at delivery against the standard weight per metre: checks when sariya arrives.
Steel bought for the chhat in the week of the neev can sit for months. Light surface rust is normal; flaking rust is not. Buy each stage when it starts, keep it on wooden blocks, covered.
Rings are cheap 8 mm bar, but they keep the column's main bars from buckling. The drawing sets the spacing, closer near beams and footings. Read: why rings matter.
If a floor may come later, the columns and footings are built for it and the column bars are left standing above the roof, coated with cement slurry. Plan: ground floor now, upper floor later.
Any size works, even a 200 sq ft room. This gives the budget range; sizes, bundles and today's price are in the sariya calculator.
A budget range, not an order list. Send your engineer's bar bending schedule with it and we'll reply with sizes, kg and today's price. Cutting and delivery are charged separately. Prices: sariya rates.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Tata Tiscon 550SD6, 8, 10, 12, 16 mm · sold per kgAsk today's rateper kg Saluja Gold TMT6, 8, 10, 12, 16 mm · the value barAsk today's rateper kgCheck the grade written in your drawing before you order. Cutting and delivery are charged separately; ask for the amount for your site (cutting and delivery). Today's price for every size: sariya rates.
About 3,500 to 5,000 kg, which is 35 to 50 quintal, for an RCC-framed house with 1000 sq ft of built-up area. That is JSW's thumb rule of 3.5 to 5 kg per sq ft. A single-storey house usually sits towards the lower end. The final figure comes from your engineer's bar bending schedule.
3.5 to 5 kg per sq ft of built-up area, counting every floor, for a frame house. It is a budgeting figure, not an order list.
Count both floors: 2000 sq ft built-up, so 7,000 to 10,000 kg (70 to 100 quintal). Buy it floor by floor and stage by stage, not in one go.
5,250 to 7,500 kg, or about 52 to 75 quintal, by the same rule.
Add the covered area of all floors. Multiply by 3.5 and by 5. That range is your budget. Before each stage, get that stage's bar bending schedule from your engineer and order from it. The sariya calculator turns the range into sizes and today's price.
JSW lists 8 mm for rings, 10 and 12 mm for slabs, and 16 mm and above for columns, beams and footings where the design needs heavier steel. Many small houses are drawn with 12 mm in columns. Go by the drawing, never thinner.
Its walls carry the load, so there are no columns and fewer beams; steel goes into the slab, the lintel band and the plinth band. No steel maker publishes a per-sq-ft figure for such houses, so take the quantity from your engineer.
Yes, and it is better for a house built in instalments. Order neev steel first, then columns, then lintel, then chhat. Cutting and delivery are charged separately each time.
10 quintal = 1 tonne = 1,000 kg. So 3.5 to 5 tonnes is 35 to 50 quintal.