Why it drips
Water grows a little as it heats. The non-return part stops it going back up the cold pipe, so the extra comes out of the valve's drain, a few drops at a time. A. O. Smith says this dripping is normal.
Most geyser trouble starts in the wall, not in the geyser: the wrong pipe on the hot side, glue where a thread should be, or a dripping valve somebody plugged. Lay the lines right before the tiles go on, because after that every fix means breaking tiles.
A geyser's thermostat can be turned up to 75 °C on the A. O. Smith model we checked. UPVC is rated only to 60 °C. CPVC is rated to 82 °C by Prince. Only CPVC covers the whole range the geyser can send.
Usual practice: the last metre or so of the cold pipe into the geyser is also CPVC, because the heat creeps back up the inlet when the geyser runs and no tap is open.
The geyser hangs on the wall; the pipes are inside it. Between them sit three short parts, and each one has a right way.
Every storage geyser comes with a brass valve for its cold inlet. Havells and A. O. Smith call it a multi-function valve: it lets out pressure, stops hot water from flowing back up the cold pipe, and lets air in when the tank is drained.
Water grows a little as it heats. The non-return part stops it going back up the cold pipe, so the extra comes out of the valve's drain, a few drops at a time. A. O. Smith says this dripping is normal.
A geyser draws a steady current for an hour at a stretch in winter. That is what heats a thin wire or a loose socket. Give it its own circuit from the board.
| Geyser | Draws | Wire | MCB |
|---|---|---|---|
| 2 kWe.g. A. O. Smith 15 L storage | 8.7 A | 2.5 sq mm × 3 | 16 A DP |
| 3 kWe.g. Havells 6 L Instanio Prime | 13 A | 2.5 sq mm × 3 | 16 A DP |
| Above 3.5 kWread the name plate | 15 A + | Send us the plate on WhatsApp | |
Amps = watts ÷ 230. Havells prints 13.04 A for its 3 kW Instanio Prime, which matches. V-Guard Classo+ 2.5 sq mm carries 18 A in a wall pipe, so the MCB is 16 A double-pole, never 20 A: between 18 and 20 A the wire overheats and a 20 A MCB never trips. B-curve is fine for a heater. Double-pole is what CPWD's wiring specification (Part I, 2013, cl. 3.14) recommends for water heaters: it cuts phase and neutral together. Earth wire the same size as phase and neutral.
Amps for every wire size: wire amps chart.
Once the wall is tiled, nobody can see the pipes again. These rules are what keep a drill bit, a nail or a leak out of them.
Easyfit is rated to 60 °C. Cheaper on the day, costly when the tiles come off. The hot side is CPVC.
CPVC needs CPVC cement; UPVC its own. Keep two tins on site, labelled. See solvents and tapes.
The drip annoys someone, so the drain gets capped. Lead it to the floor trap instead. A. O. Smith says blocking it voids the warranty.
A 2 kW geyser draws 8.7 A for an hour at a time. It needs its own 16 A double-pole point on 2.5 sq mm wire. MCB tripping?
The earth wire must reach the geyser point, and the RCCB must trip when its test button is pressed. Check both before the geyser goes on.
Use brass-insert threaded CPVC fittings at the geyser and mixer points, and Teflon on the threads, not solvent. Leaking joint?
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
CPVC pipes and fittingsGeyser to hot taps · ½″, ¾″ · elbows, tees, brass-insert MTA/FTAAsk today's rateper 3 m Truzo CPVC solventFor CPVC only · 100 ml₹ 175per tin CPVC MTA / FTA adaptorsCPVC to UPVC and to the hose · CPVC ¾ × ½Ask today's rateper pieceAnything not on the rack today, any size or a geyser itself, we can order for you; ask on WhatsApp how long it takes. Today's prices: pipe rates · electrical rates. Pipe sizes for the whole house: tank to bathroom.
CPVC, from the geyser outlet to every hot tap and the shower mixer. Prince rates its SmartFit Plus CPVC up to 82 °C. UPVC such as Prince Easyfit is rated only from 5 to 60 °C, and a geyser thermostat can be set as high as 75 °C (A. O. Smith manual).
No. Prince rates Easyfit UPVC for 5 to 60 °C. Geyser water can be hotter, and the pipe softens and the joints start to weep, usually inside the tiled wall. The cold supply to the bathroom stays UPVC.
Water expands as it heats. The valve's non-return part stops it going back up the cold pipe, so a little escapes from the valve's drain. A. O. Smith says this dripping is normal. Never plug or remove the valve; lead its drain to the floor trap instead. A steady stream, not drops, is a fault: call the geyser's service centre.
Its own line of 2.5 sq mm wire (phase, neutral and earth) on a 16 A double-pole MCB. A 2 kW geyser draws about 8.7 A and a 3 kW geyser about 13 A, both inside 16 A. V-Guard Classo+ 2.5 sq mm carries 18 A in a wall pipe, so never put a 20 A MCB on it. Full table: wire amps chart.
Half inch for the geyser connection and for each tap; the geyser's inlet and outlet are ½″ BSP threads on the A. O. Smith model we checked. A half-inch CPVC pipe is 15.9 mm outside and a half-inch Easyfit UPVC pipe is 21.3 mm, so they join through threaded adaptors, not glue.
Usual practice is to make the last stretch of the cold pipe into the geyser CPVC too, because heat creeps back up the inlet. The rest of the cold supply stays UPVC.
The manual we checked asks for braided flexible hoses rated at least 8 bar. A hose also lets the geyser come off the wall for service without cutting any pipe. So: CPVC in the wall, brass-threaded point at the tile, braided hose to the geyser.
Twenty years on sites around Muzaffarpur, including more re-tiled bathrooms than he would like, most of them for a UPVC pipe behind a geyser. Every figure on this page was checked against the maker's own product page or manual on 13 Nov 2026. Where makers give different figures, the page says so and uses the safer one.
WhatsApp a photo of your open bathroom wall with the geyser point marked. We'll look at it with you: CPVC on the hot side, the right adaptors, the valve drain and the 16 A point.