How many cement bags for a 1000 sq ft house: slab, walls, plaster, floor

The short answer
350–420
Brick walls, RCC roofThe usual one-storey Bihar house. Our worked house below: about 365.
400–500
RCC frameColumns and beams carry the roof: 0.4 to 0.5 bag per sq ft.
96
Roof slab alone5 inch, M20 concrete. 77 to 125 bags from 4 to 6 inch and M20 to M25.

The slab, plaster and floor are inside these totals, not on top. For two floors, count the built-up area of both. Use these figures to set your budget and order stage by stage. They are not a bill of quantities.

Where 365 bags go in one house
Section through a one-storey brick house, with cement bags for each stage Cut through a 1000 sq ft brick house with an RCC roof. Foundation and plinth about 85 bags, walls with lintel band and chhajja about 70, roof slab with stair and parapet about 110, plaster about 50, floor about 50. About 365 bags in all, no wastage added. 1 2 3 4 5 1 2 3 4 5 FoundationWallsRoofPlasterFloor ≈ 85 bags≈ 70 bags≈ 110 bags≈ 50 bags≈ 50 bags PCC, footing, plinthbrick, lintel band5″ slab, stair, parapetinside, outside, ceilingPCC, tile bed, apron About 365 bags in all 85701105050 1 foundation2 walls3 roof4 plaster5 floor 50 kg bags · no wastage added · drawing not to scale
One storey, 40 × 25 ft, 9-inch brick walls, 5-inch RCC roof, tiled floor. Worked out with UltraTech's published concrete figures and standard estimating figures. Every size is in the stage table.
First question

What carries your roof decides the total

Ask this before any number. Then check what "1000 sq ft" means on your drawing.

ABrick walls carry the roof

350–420 bags. The usual Bihar house: 9-inch walls, an RCC slab, and a concrete band over the doors and windows. Most cement goes into the slab, the brick mortar and the plaster. Our worked house comes to about 365.

BColumns and beams carry it

400–500 bags, or 0.4 to 0.5 bag per sq ft. Column footings, columns, and beams at plinth and roof are extra concrete, and the walls are still there. The same house built as a frame comes to about 450.

CCount every floor

The bags-per-sq-ft rule works on built-up area: the covered area wall to wall, on every floor. Not the plot, not the carpet area. A ground and first floor of 1000 sq ft each is 2000 sq ft for this rule.

The ranges on one scale
Cement bag ranges for a 1000 sq ft house Brick house with RCC roof 350 to 420 bags, worked house 365. RCC frame 400 to 500, worked frame about 450. Roof slab alone 77 to 125. Plaster of the whole house about 50 to 90. The slab and plaster are already inside the two totals. 0100200300400500 Brick walls, RCC roofRCC frame Roof slab alone, 4–6″Plaster, whole house 350420 400 77125 5090 worked house 365frame about 450 already insidethe totals above,not extra
Slab: M20 to M25 concrete (UltraTech's figures). Plaster: about 50 by arithmetic, up to 90 on UltraTech's own plaster figure. All one storey, 50 kg bags.
Where the bags go

One worked house, stage by stage

A plain Bihar house, worked out part by part, so you can see what each stage takes and when to order it. Your drawing will differ. The method stays the same.

The worked house, plan
Plan of the worked house 40 by 25 feet outside. Two bedrooms on the left, a hall in the middle, kitchen, stair and toilet on the right. Thick walls are 9 inch and carry the roof; thin walls are 4.5 inch partitions. 40 ft 25 ft BedroomBedroomHallKitchenStairToilet 13 × 12 ft13 × 12 ft14 × 25 ft13 × 10 ft 9″ wall · 187 ft 4.5″ wall · 30 ft window Wall lengths are measured along the centre of each wall.
Thick red: 9-inch walls that carry the roof. Thin: 4.5-inch partitions. 10 ft walls, 2.5 ft plinth, 3 ft parapet, 7 doors, 8 windows.
Stage and what goes in itBags
1Foundation and plinthPCC bed 6″, 1:4:8: 27 · brick footing and plinth wall, 1:6: 43 · plinth band 6″, M20: 16Order just before the digging ends.≈ 85
2Walls up to the roof9″ brickwork, 1:6: 41 · 4.5″ partitions, 1:4: 5 · lintel band, M20: 16 · chhajjas: 7In lots, as the walls rise.≈ 70
3RoofSlab 5″, M20: 96 · stair to the roof: 10 · parapet 3 ft, 1:4: 7All of it, two days before the dhalai. A slab is poured in one go.≈ 110
4PlasterInside 2,740 sq ft, 12 mm, 1:6: 17 · outside 1,945 sq ft, 18 mm, 1:4: 25 · parapet: 3 · ceiling 900 sq ft, 8 mm, 1:3: 6Room by room. Keep 10–15 extra; the reason is in the next section.≈ 50
5FloorPCC 3″, 1:4:8: 22 · tile bed 20 mm, 1:4: 13 · cement slurry under tiles: 6 · plinth protection outside, 1:3:6: 10Before the tiling starts.≈ 50
Whole houseAdd about 5% for wastage on a tidy site: about 385 bags to plan for.≈ 365
What the worked house is. One storey, 40 × 25 ft outside (1,000 sq ft built-up). Footing 3 ft below ground on a 3 ft wide PCC bed. Plinth 2.5 ft above ground. 9-inch walls on the outside and the main inside lines, 4.5-inch partitions, a lintel band and a plinth band, which IS 4326 asks for in brick houses in an earthquake zone like ours. 5-inch roof slab, a stair to the roof, tiles on 900 sq ft of floor. No septic tank, boundary wall or water tank: count those separately.
Check it yourself

Every bag count uses the same four steps

Thekedars, cement companies and our calculator all work this way. Once you know the steps, you can check any figure you are given. Ask for the mix and thickness behind it.

Working out the cement for a 1000 sq ft, 5 inch roof slab Wet volume 92.9 square metres times 0.127 metres is 11.8 cubic metres. Times 1.54 for dry materials is 18.2. Divided by 5.5 for an M20 mix of 1 to 1.5 to 3 is 3.30 cubic metres of cement. Times 1,440 kilograms, divided by 50, is about 96 bags (rounded up). 1000 sq ft 5″ 1 2 3 4 Wet volumeDry volumeCement share of the mixInto bags area × thickness · 1000 sq ft = 92.9 sq mdry cement, balu, gitti fill more spaceM20 = 1 : 1.5 : 3, so 5.5 partscement = 1,440 kg per m³ · bag = 50 kg 92.9 × 0.127 = 11.8 m³11.8 × 1.54 = 18.2 m³18.2 ÷ 5.5 = 3.30 m³3.30 × 1,440 ÷ 50 ≈ 96 bags Same as UltraTech's M20 working: about 403 kg,or 8 bags, per m³ of concrete. 11.8 × 8.06 ≈ 96.
Bags of cement (50 kg) for eachBags
m³ of RCC, M20 (1:1.5:3)UltraTech: about 403 kg. Slabs, beams, columns, footings.8.1
m³ of RCC, M25UltraTech: about 443 kg. UltraTech recommends it for slabs.8.9
m³ of PCC, 1:3:6 / 1:4:8Plinth protection / foundation bed and floor base4.4 / 3.4
m³ of brickwork, 1:6 / 1:4About 0.31 m³ of dry mortar in each m³ of brickwork1.3 / 1.8
100 sq ft of plaster, inside12 mm, 1:6, as UltraTech gives for inside walls0.6
100 sq ft of plaster, outside18 mm, 1:4 (UltraTech: 15–20 mm, 1:4)1.3
100 sq ft of ceiling plaster8 mm, 1:3 (UltraTech: 6–10 mm, 1:3)0.7

Dry-volume factor 1.54 for concrete (UltraTech), about 1.33 for mortar (standard figure).

Roof slab over 1000 sq ftM20M25
4 inch7784
5 inch96105
6 inch115125
Where the figures disagree, and which one we use. Slab concrete. UltraTech calls M20 "widely used" for house slabs and recommends M25 for slabs. IS 456 allows nothing weaker than M20 in any RCC. Your engineer's drawing decides. If it doesn't say, keep the M25 figure ready, so you don't run short in the middle of a dhalai. Plaster. The arithmetic gives 0.6 bag per 100 sq ft of 12 mm plaster. UltraTech's own plaster page says 1 to 1.5 bags. The gap is real walls: brick faces are never flat, so the plaster goes on thicker in the dips. We count by the arithmetic and tell you to keep 10–15 extra bags at the plaster stage. That is the safer choice.

The full slab working, with balu and gitti, is in how much cement for a chhat dhalai. For any part of your own drawing, use the cement, sand and aggregate calculator.

Same size, different count

Why your neighbour's 1000 sq ft took more bags

Usually nobody cheated. Each of these moves the count, and the last two are where bags go missing.

plot 1,000 built-up first 1,000ground 1,000 = 2,000 sq ft

"1000 sq ft" of what?

Can double the answer

The rule works on built-up area of all floors. Plot area and carpet area give the wrong count. Ask which one the thekedar means.

9 inch4.5 inch wall seen from above half the mortar

9-inch or 4.5-inch walls

More 9-inch walls, more mortar

Over the same length, a 9-inch wall holds about twice the mortar of a 4.5-inch one. Inside walls that carry the roof are 9-inch too.

4″ · 775″ · 966″ · 115 1000 sq ft, M20, bags

Slab thickness

4 to 6 inch moves about 40 bags

The slab is the biggest single pour. One inch more over 1000 sq ft is about 19 bags at M20. Read the thickness off the drawing.

75 · 1:2:496 · M20 5″ slab, quoted online 5″ slab, as it should be

A low count from a weak mix

1:2:4 is not slab concrete

Some pages work a 5-inch slab out at 75 bags using 1:2:4. That is about M15, and IS 456 allows nothing below M20 in reinforced concrete. Don't plan a slab on a mix you shouldn't pour.

25 mm in the dips12 mm on the high bricksplus what falls on the floor

Uneven walls, thicker plaster

Plaster can take half as much again

This is why UltraTech's own figure (1 to 1.5 bags per 100 sq ft) is above the arithmetic. Straight brickwork with even joints saves plaster cement.

GOING HARD ON PLANKS, COVERED

Bags lost on site

Every hard bag is pure loss

Bags left on damp ground, or mortar mixed and left to set, go to waste. Stack on planks, away from the wall, covered, oldest bags first. Buy for the stage in front of you. Delivery check.

Your house

A planning count for your house

Put in your built-up area and floors. You get the whole-house range, the slab worked out exactly, and what is left for the other stages. For each part's own numbers, use the full calculator.

0.35–0.42 bag per sq ft of built-up area, all floors.

Your cement count

Whole house—planning range, 50 kg bags
Roof slab——
Foundation, walls, plaster, floor—Order in lots, stage by stage
To plan for, with 5% wastage—Cement cost: bags × today's bag price · Ask rate
Cement totalAsk rate
Send this count on WhatsApp

Planning figures, not a bill of quantities. Each part of your drawing: cement, sand and aggregate calculator. Cutting and delivery are charged separately; ask for the amount for your site.

The rest of the material for the same house: sariya kitna lagega · bricks for 1000 sq ft · balu and gitti for 1000 sq ft · the whole budget: cost of a 1000 sq ft house.

Questions people ask us

Short answers

How many cement bags for a 1000 sq ft house?

For one storey with brick walls and an RCC roof, 350 to 420 bags of 50 kg. For an RCC frame with columns and beams, 400 to 500 bags. Our worked Bihar house comes to about 365 bags, or about 385 with 5% wastage. These are planning figures, not a bill of quantities.

How many bags for a 1000 sq ft roof slab?

At M20, about 77 bags for a 4-inch slab, 96 for 5-inch and 115 for 6-inch. At M25, which UltraTech recommends for slabs, 84, 105 and 125. Beams and the stair are extra. Full working: chhat dhalai cement.

How much cement for 1000 sq ft of plaster?

About 6 bags at 12 mm and 1:6, about 8.5 bags at 1:4, by the standard arithmetic. UltraTech's plaster page says 1 to 1.5 bags per 100 sq ft, so 10 to 15 bags, because real walls are uneven. The plaster of a whole 1000 sq ft house (inside, outside and ceiling) is about 50 bags by arithmetic.

Cement kitna lagega kaise nikale? (how do I work it out?)

Area × thickness gives the wet volume. Multiply by 1.54 for concrete or about 1.33 for mortar. Take the cement share of the mix (1 part in 5.5 for M20). Multiply by 1,440 kg and divide by 50 for bags. The calculator does this for each part.

Does a ground + first floor house take double?

Close to it. Use the built-up area of both floors: 2000 sq ft at 0.35 to 0.42 bag per sq ft is 700 to 840 bags for a brick house. The two floors share one foundation, so the true count is a little lower, but the foundation must be made for two floors. Plan on the range.

How many bags per sq ft?

0.35 to 0.42 bag per sq ft of built-up area for a brick house with an RCC roof, and 0.4 to 0.5 for an RCC frame, all floors counted.

What will the cement cost?

Your bag count × today's price for the bag you choose, from the cement rate page. Cutting and delivery are charged separately. Cement is only one line of the house budget: cost of a 1000 sq ft house.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Civil engineer at our Reva Road store, Muzaffarpur. He worked out the house on this page part by part on 12 Nov 2026, using UltraTech's published mix figures and standard estimating figures. Where the figures disagree, the page says so and uses the safer one.

Where the numbers come from

  1. UltraTech, M20 concrete ratio and mix calculation: 1:1.5:3, dry volume 1.54 m³ per m³, cement 1,440 kg/m³, about 403 kg (8 bags) per m³; widely used for slabs, beams, columns and footings.
  2. UltraTech, Calculation guide for M25 concrete: 1:1:2, 443 kg (about 9 bags) per m³; recommended for slabs.
  3. UltraTech, How to calculate the ideal plastering ratio: inside 1:6 at 12 mm, outside 1:4 at 15–20 mm, ceiling 1:3 at 6–10 mm; FAQ: 1 to 1.5 bags per 100 sq ft at 12 mm.
  4. BIS, IS 456:2000, Table 5: M20 is the lowest grade allowed for reinforced concrete.
  5. BIS, IS 4326: concrete bands in brick buildings in earthquake zones.
  6. Standard estimating figures: 1.33 dry-volume factor for mortar, about 0.31 m³ of dry mortar per m³ of brickwork, 50 kg bag. The ranges 350–420 and 400–500 bags (0.4–0.5 bag per sq ft) are the ones builders and cement companies quote; our worked house checks them.

Send us your plan

We'll count the cement for each stage, with today's price, on WhatsApp. Send photos of the sariya on WhatsApp before dhalai and we'll check them with you.