Home›Calculators›House construction cost
Calculator · Bihar

House construction cost calculator for Bihar: sq ft or katha, lenter or tin roof, with the full material list

Prices come from today's rate board at our Rewa Road store, Muzaffarpur. Rates: Ask rate until the morning update.

The short answer
House cost = material list × today's rate + labour, worked out separately

Most calculators give one rupee figure from a city average. This one gives the list you will actually buy: cement bags, sariya kg by bar size, bricks, balu and gitti in cft, tiles, putty, paint, pipes and wire. It takes your plot in katha and dhur, a tin roof and a raised flood plinth. Labour is never mixed into the material.

0.4–0.5
Bag of cement per sq ftBuilt-up area, lenter house with RCC frame. Standard thumb rule.
3.5–6 kg
Sariya per sq ftRCC frame, one storey at the low end, G+2 at the high end.
Plot ≠ house
Price the covered areaCovered area × floors, never the katha on the deed.
What the calculator counts
Plan of a plot showing what is and is not in the estimate The house itself, from neev to paint, with its pipes and wire, is in the list. The boundary wall, borewell, septic tank, soak pit and roof water tank are drawn dashed in red: they are not in the list and must be added separately, as must labour. Boundary wall · not counted ROAD RoomRoomKitchenBath IN THE LIST Tank Septic Soak pit Borewell In the list:neev, plinth, walls, roof, plaster, floor,putty and paint, pipes and wire Add separately:these, plus doors, windows and labour
Not to scale. The list stops at the house walls. Everything drawn dashed is real money in Bihar and is listed under not in the list.
The calculator

Your house, your list

Every quantity comes out as a low and a high number from standard thumb rules, labelled as estimates. Buy to the high number; your naksha and your engineer's drawing decide the final order.

Tashya Ventures · house material estimate

Area

Outside wall to outside wall. Not the plot.

Floors

"Upper later" prices one floor, with footings and columns made ready for the next one.

What carries the house

Brick walls carrying the slab, with no columns, is the usual village house. The village brick house.

Roof
Plinth
Finish

Changes the tiles and paint, and whether the walls get putty. Cement, sariya and bricks stay the same.

Bathrooms and labour

Labour-only rates from your own thekedars, for the same scope. Leave blank if you don't have them yet. How labour is priced.

Your list

Material totalat today's rate, high numbersAsk rate
Labour, kept separateyour thekedar's quote × built-upAsk rate
House totalAsk rate
Per sq ft of built-upAsk rate
Send this list on WhatsApp

Quantities are planning figures from standard thumb rules, not a bill of quantities. Cutting and delivery of sariya and cement are charged separately; ask for the amount for your site (delivery). Order in stages with the new house material list.

How the numbers are worked out

The thumb rules behind every line, in the open

Built-up area means the covered area of all floors added together. Each figure below is labelled: Thumb rule is a standard planning figure, Maker is from the maker's own sheet, Usual practice is what a typical Bihar house has.

Per sq ft of built-upRCC frameBrick walls carry the slab
Structure, lenter roof, normal plinth
Cement, 50 kg bag Thumb ruleIncludes footing, slab, brickwork, plaster and floor base0.40–0.500.35–0.42
Sariya (TMT), kg Thumb ruleFrame: 3.5–4.5 for one storey, 4–5 for G+1, 4.5–6 for G+23.5–61.5–2.2
Balu (sand), cft Thumb rule1.2–1.81.3–1.8
Gitti (stone chips), cft Thumb rule1.0–1.350.6–0.9
Bricks, number Thumb ruleRough. Count from your walls before you order: bricks for 1000 sq ft8–1011–13
Binding wire Thumb rule8–10 kg per tonne of sariya
Changes for your choices
Sheet roof instead of lenter Thumb rulePer sq ft of the top roof: no slab concrete or slab mesh−0.075–0.112 bag
−0.6–1.1 kg
−0.075–0.112 bag
−1.0–1.5 kg
Roof sheets Maker1.05 m wide; about 91% of a 3 m sheet covers after overlaps (Everest, Charminar). Roof taken as floor area + 8–15% for slope and overhang3 m sheets = roof ÷ 30.9 sq ft
Ground floor made ready for an upper floor Thumb rule+0.4–0.5 kg
+0.02–0.03 bag
+1 brick
+0.01–0.02 bag
Each foot of plinth above 1.5 ft Thumb ruleWall length round and through the plinth taken as 7 × √(floor area); 9-inch wall, 10 bricks per sq ft of wall face; 1:6 mortar10 bricks per ft of wall per ft of height, plus filling
Plinth filling Thumb rule90% of floor area × plinth height, cft
Finishing
Inside walls and ceilings to paint Thumb ruleWalls 2.5 × carpet area, ceiling 1 × carpet (Asian Paints' calculator method); carpet ≈ 80% of built-up; tiled walls taken off2.8 × built-up, sq ft
Outside walls to paint Thumb rule4.4 × √(floor area) × (10 ft per floor + 3 ft parapet) × 0.85
WallCare putty, 2 coats Maker17–20 sq ft per kg (Birla White)
ActivCoat Interior primer Maker110–140 sq ft/L on plaster, 170–200 on putty, per coat (Birla White)
Inside paint, 2 coats MakerStyle Color Smart 120–140 · Calista Ever Wash Shine 130–150 sq ft/L (Birla Opus)
Outside primer and paint MakerPrimer 80–100 sq ft/L · paint 50–60 sq ft/L for 2 coats (Birla Opus)
Floor tiles Usual practice0.85–0.92 × built-up, less bathroom floors
Bathroom tiles Usual practiceFloor 36–45 sq ft, walls 140–180 sq ft each; kitchen wall 30–45
Pipes, wire, waterproofing
Water pipe (UPVC, CPVC) Usual practice25 m per bathroom + 12 m kitchen + 6 m per floor, ±15%
SWR drainage pipe Usual practice9 m per bathroom + 6 m kitchen + 3 m per floor, ±15%
Conduit 20/25 mm Usual practice0.18–0.25 m per sq ft
Wire, 90 m coils Usual practiceAt least 3 coils of each size: red, black and green1.5 sq mm: 1 per 200–250 sq ft · 2.5 sq mm: 1 per 350–450 sq ft
WP+200 waterproofing MakerRoof slab and outside plaster only200 ml per 50 kg bag of cement (UltraTech)

Muzaffarpur is in earthquake Zone IV under IS 1893:2016. The sariya figure is for budgeting only. Your engineer's bar bending schedule decides the steel, and we never advise trimming it to save money. Before dhalai, send photos of the bars on WhatsApp and we will look at them with you (free slab check).

Only here

Four Bihar choices, and what each one does to your list

No other calculator we found takes katha, a raised flood plinth or a sheet roof. These are the choices that move a Bihar house bill most.

plot: 1 katha = 20 dhur house 1 katha 1,361 sq ft house covers 70% 953 sq ft per floor price this, × floors

Plot in katha and dhur

Covered area, not plot area

Enter katha and dhur straight from the deed, pick the katha size on your papers, and say how much of the plot the house covers. Pricing the whole plot is the most common way people over-budget. Katha to sq ft.

Normal 1.5 ft Raised 3 ft EXTRA more bricks round the edge, more filling inside

Raised plinth for a flood area

Bricks and filling rise with every foot

Set the height in feet. Each foot above the normal 1.5 ft adds brickwork round and through the plinth and filling inside it. For a 1,000 sq ft floor, going from 1.5 to 3 ft adds roughly 3,300 bricks and 1,350 cft of filling.

Lenter cement, sariyaand gitti Sheet roof sheets onpurlins

Lenter or tin / cement sheet

The slab is where cement and sariya go

With a sheet roof the list drops the slab concrete and mesh and adds sheets, counted from the makers' 91% cover. Purlin size depends on your span, so we price it when you send the span. A sheet goes on the top floor only. Sheet-roof house cost.

upper floor, later built now bars left out

Ground now, upper floor later

A little more steel now saves breaking later

Most families here build one floor and add the next when money comes. The calculator prices one floor plus heavier footings and columns, with bars left sticking out. Adding them later is far dearer than now. Ground floor now, upper later.

Before you trust any total

What is in the list, and what you add yourself

Online per-sq-ft figures for Muzaffarpur differ by a quarter, and not one says what it includes. Here is exactly what ours covers.

In the list

  • Neev, plinth and plinth filling
  • Columns, beams and lenter, or walls and a sheet roof
  • Brickwork, plaster and the floor base
  • Floor and bathroom tiles, putty, primer and paint, inside and out
  • Water and drain pipes, conduit and house wire
  • Waterproofing liquid for the roof slab and outside plaster, optional

Not in the list: add separately

Labour, kept separate

Why we don't print a labour rate, and what to do instead

We looked in November 2026 and found no reliable published labour rate for Muzaffarpur. Most figures online are computed for other cities. So the calculator takes your own thekedars' quotes and keeps them on their own line.

1Labour-only per sq ft

The thekedar and his gang do the work, you buy the material. Ask two or three for the same scope, in writing. Put both quotes in the calculator to see the range.

2Daily wage

Mistri and helper paid by the day, good for small jobs and finishing. The legal floor: Bihar's minimum wage from 1 April 2026 is about ₹436 a day unskilled and ₹551 skilled, as reported by compliance websites. Market rates are normally higher.

3Slab-day lump sum

One agreed amount for dhalai day, with a larger gang and a mixer. Ask the gang size and whether curing days are inside the price.

Two equal rates can cover different work. Check who pays for shuttering, scaffolding and shifting material before you compare. Labour and thekedar rates in Muzaffarpur.

On our shelf for this list

Every line in the list, from one store

Every product here can be ordered. Anything not on the shelf, we order for you; ask on WhatsApp how long it takes. Today's prices: rate board.

Questions people ask us

Short answers

Ghar banane me kitna kharcha aata hai?

Material plus labour. The material comes from your built-up area: for a lenter house with an RCC frame, the standard thumb rule is about 0.4 to 0.5 bag of cement and 3.5 to 4.5 kg of sariya per sq ft for one storey. Put your details in the calculator above; it gives the full list at today's rate. Then add your thekedar's labour rate times the built-up area.

What is the construction cost per sq ft in Bihar?

Figures published in 2026 for Muzaffarpur run from about ₹1,750 (NoBroker) to ₹1,896 (InfraLens) per sq ft for a standard house, and none of them says what is inside. Your own figure is your total divided by your built-up area; the calculator shows it once the day's rates are in. More on this: cost per sq ft in Muzaffarpur.

How much does a 1000 sq ft house cost in a village?

A village house is often brick walls carrying a lenter, with no columns. Choose "Brick walls carry the slab" above: for 1,000 sq ft that is about 350 to 420 bags of cement and 1,500 to 2,200 kg of sariya by the thumb rule, against 400 to 500 bags and 3,500 to 4,500 kg for an RCC frame. Worked out in full: 1000 sq ft house cost and the village brick house.

Can I enter my plot in katha? Which katha size is right?

Yes. 1 katha is 20 dhur. The katha is not one size across Bihar: 1,361.25 sq ft comes from a bigha of 27,225 sq ft, and some converters give 1,500 sq ft for Muzaffarpur. Use the figure on your deed or ask at the registry office, and type it in. The calculator then takes only the covered part of the plot.

Does the estimate include boundary wall, borewell and septic tank?

No. Boundary wall, borewell, septic tank, soak pit, water tank, doors, windows, grills, sanitaryware, switches and fans are left out. They are listed in not in the list with a page for each.

Why does a raised flood plinth cost more, and how high should it be?

Every extra foot needs more brickwork round the house and more filling inside it. For a 1,000 sq ft floor, raising it from 1.5 to 3 ft adds roughly 3,300 bricks and 1,350 cft of filling. We found no official plinth height for Muzaffarpur: fix yours from the highest flood your neighbours remember, with a margin, and confirm it with your engineer. How high in a flood area.

Tin roof now, lenter later: is that possible?

Only if the walls and footings are built for a slab from the start. Choose "Ground now, upper later" and price both roofs to see the difference. Sheet-roof house cost.

Is labour included in the total?

Labour is kept on its own line. Enter one or two labour-only quotes per sq ft from your thekedars and the calculator multiplies them by the built-up area. Bihar's minimum wage from 1 April 2026 is about ₹436 a day for unskilled and ₹551 for skilled work; market rates are usually above it.

Where the numbers come from

  1. Cement, sariya, balu, gitti and brick per sq ft: standard planning thumb rules used across India, rounded into ranges. Our working: thumb rules for a house, cement for 1000 sq ft, sariya per sq ft, balu and gitti for 1000 sq ft. Slab mesh 0.6–1.1 kg per sq ft: sariya in a roof slab.
  2. Birla White, wall putty work: 17–20 sq ft per kg. ActivCoat Interior primer: 110–140 sq ft/L on plaster, 170–200 on putty, per coat.
  3. Birla Opus product sheets: Style Color Smart 120–140 sq ft/L, Calista Ever Wash Shine 130–150, exterior primer 80–100, Style Power Bright 50–60 for 2 coats.
  4. Asian Paints, Paint Budget Calculator method: walls = carpet area × 2.5, ceiling = carpet area.
  5. Everest and Charminar (BirlaNu) published sheet data: 6 mm, 1.05 m wide, about 91% of a 3 m sheet covers after overlaps. See roofing sheets.
  6. UltraTech, Weather Pro WP+200: 200 ml per 50 kg bag of cement.
  7. Bihar minimum wages from 1 April 2026 (about ₹436 unskilled, ₹551 skilled per day), as reported by compliance websites; see labour rates.
  8. Katha: 1 bigha = 20 katha = 400 dhur. 1,361.25 sq ft per katha from a bigha of 27,225 sq ft; 1,500 sq ft is the figure IndiaLandConverter lists for Muzaffarpur (checked 12 Nov 2026). Confirm on your deed.
  9. Per-sq-ft figures quoted in the questions: NoBroker house construction cost calculator page (updated 24 Feb 2026), InfraLens construction cost calculator (Muzaffarpur, Tier 3).

Send us your naksha or your list

We'll check the quantities with you and send back today's price for each line on WhatsApp. Before dhalai, send photos of the bars and we'll look at them with you.