Plot in katha and dhur
Enter katha and dhur straight from the deed, pick the katha size on your papers, and say how much of the plot the house covers. Pricing the whole plot is the most common way people over-budget. Katha to sq ft.
Prices come from today's rate board at our Rewa Road store, Muzaffarpur. Rates: Ask rate until the morning update.
Most calculators give one rupee figure from a city average. This one gives the list you will actually buy: cement bags, sariya kg by bar size, bricks, balu and gitti in cft, tiles, putty, paint, pipes and wire. It takes your plot in katha and dhur, a tin roof and a raised flood plinth. Labour is never mixed into the material.
Every quantity comes out as a low and a high number from standard thumb rules, labelled as estimates. Buy to the high number; your naksha and your engineer's drawing decide the final order.
Quantities are planning figures from standard thumb rules, not a bill of quantities. Cutting and delivery of sariya and cement are charged separately; ask for the amount for your site (delivery). Order in stages with the new house material list.
Built-up area means the covered area of all floors added together. Each figure below is labelled: Thumb rule is a standard planning figure, Maker is from the maker's own sheet, Usual practice is what a typical Bihar house has.
| Per sq ft of built-up | RCC frame | Brick walls carry the slab |
|---|---|---|
| Structure, lenter roof, normal plinth | ||
| Cement, 50 kg bag Thumb ruleIncludes footing, slab, brickwork, plaster and floor base | 0.40–0.50 | 0.35–0.42 |
| Sariya (TMT), kg Thumb ruleFrame: 3.5–4.5 for one storey, 4–5 for G+1, 4.5–6 for G+2 | 3.5–6 | 1.5–2.2 |
| Balu (sand), cft Thumb rule | 1.2–1.8 | 1.3–1.8 |
| Gitti (stone chips), cft Thumb rule | 1.0–1.35 | 0.6–0.9 |
| Bricks, number Thumb ruleRough. Count from your walls before you order: bricks for 1000 sq ft | 8–10 | 11–13 |
| Binding wire Thumb rule | 8–10 kg per tonne of sariya | |
| Changes for your choices | ||
| Sheet roof instead of lenter Thumb rulePer sq ft of the top roof: no slab concrete or slab mesh | −0.075–0.112 bag −0.6–1.1 kg | −0.075–0.112 bag −1.0–1.5 kg |
| Roof sheets Maker1.05 m wide; about 91% of a 3 m sheet covers after overlaps (Everest, Charminar). Roof taken as floor area + 8–15% for slope and overhang | 3 m sheets = roof ÷ 30.9 sq ft | |
| Ground floor made ready for an upper floor Thumb rule | +0.4–0.5 kg +0.02–0.03 bag | +1 brick +0.01–0.02 bag |
| Each foot of plinth above 1.5 ft Thumb ruleWall length round and through the plinth taken as 7 × √(floor area); 9-inch wall, 10 bricks per sq ft of wall face; 1:6 mortar | 10 bricks per ft of wall per ft of height, plus filling | |
| Plinth filling Thumb rule | 90% of floor area × plinth height, cft | |
| Finishing | ||
| Inside walls and ceilings to paint Thumb ruleWalls 2.5 × carpet area, ceiling 1 × carpet (Asian Paints' calculator method); carpet ≈ 80% of built-up; tiled walls taken off | 2.8 × built-up, sq ft | |
| Outside walls to paint Thumb rule | 4.4 × √(floor area) × (10 ft per floor + 3 ft parapet) × 0.85 | |
| WallCare putty, 2 coats Maker | 17–20 sq ft per kg (Birla White) | |
| ActivCoat Interior primer Maker | 110–140 sq ft/L on plaster, 170–200 on putty, per coat (Birla White) | |
| Inside paint, 2 coats Maker | Style Color Smart 120–140 · Calista Ever Wash Shine 130–150 sq ft/L (Birla Opus) | |
| Outside primer and paint Maker | Primer 80–100 sq ft/L · paint 50–60 sq ft/L for 2 coats (Birla Opus) | |
| Floor tiles Usual practice | 0.85–0.92 × built-up, less bathroom floors | |
| Bathroom tiles Usual practice | Floor 36–45 sq ft, walls 140–180 sq ft each; kitchen wall 30–45 | |
| Pipes, wire, waterproofing | ||
| Water pipe (UPVC, CPVC) Usual practice | 25 m per bathroom + 12 m kitchen + 6 m per floor, ±15% | |
| SWR drainage pipe Usual practice | 9 m per bathroom + 6 m kitchen + 3 m per floor, ±15% | |
| Conduit 20/25 mm Usual practice | 0.18–0.25 m per sq ft | |
| Wire, 90 m coils Usual practiceAt least 3 coils of each size: red, black and green | 1.5 sq mm: 1 per 200–250 sq ft · 2.5 sq mm: 1 per 350–450 sq ft | |
| WP+200 waterproofing MakerRoof slab and outside plaster only | 200 ml per 50 kg bag of cement (UltraTech) | |
Muzaffarpur is in earthquake Zone IV under IS 1893:2016. The sariya figure is for budgeting only. Your engineer's bar bending schedule decides the steel, and we never advise trimming it to save money. Before dhalai, send photos of the bars on WhatsApp and we will look at them with you (free slab check).
No other calculator we found takes katha, a raised flood plinth or a sheet roof. These are the choices that move a Bihar house bill most.
Enter katha and dhur straight from the deed, pick the katha size on your papers, and say how much of the plot the house covers. Pricing the whole plot is the most common way people over-budget. Katha to sq ft.
Set the height in feet. Each foot above the normal 1.5 ft adds brickwork round and through the plinth and filling inside it. For a 1,000 sq ft floor, going from 1.5 to 3 ft adds roughly 3,300 bricks and 1,350 cft of filling.
With a sheet roof the list drops the slab concrete and mesh and adds sheets, counted from the makers' 91% cover. Purlin size depends on your span, so we price it when you send the span. A sheet goes on the top floor only. Sheet-roof house cost.
Most families here build one floor and add the next when money comes. The calculator prices one floor plus heavier footings and columns, with bars left sticking out. Adding them later is far dearer than now. Ground floor now, upper later.
Online per-sq-ft figures for Muzaffarpur differ by a quarter, and not one says what it includes. Here is exactly what ours covers.
We looked in November 2026 and found no reliable published labour rate for Muzaffarpur. Most figures online are computed for other cities. So the calculator takes your own thekedars' quotes and keeps them on their own line.
The thekedar and his gang do the work, you buy the material. Ask two or three for the same scope, in writing. Put both quotes in the calculator to see the range.
Mistri and helper paid by the day, good for small jobs and finishing. The legal floor: Bihar's minimum wage from 1 April 2026 is about ₹436 a day unskilled and ₹551 skilled, as reported by compliance websites. Market rates are normally higher.
One agreed amount for dhalai day, with a larger gang and a mixer. Ask the gang size and whether curing days are inside the price.
Two equal rates can cover different work. Check who pays for shuttering, scaffolding and shifting material before you compare. Labour and thekedar rates in Muzaffarpur.
Every product here can be ordered. Anything not on the shelf, we order for you; ask on WhatsApp how long it takes. Today's prices: rate board.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
UltraTech SuperFootings, columns, slab₹ 435per 50 kg bag UltraTech PPCBrickwork, plaster, floor₹ 330per 50 kg bag UltraTech Weather PlusRoof and damp places₹ 440per 50 kg bagMaterial plus labour. The material comes from your built-up area: for a lenter house with an RCC frame, the standard thumb rule is about 0.4 to 0.5 bag of cement and 3.5 to 4.5 kg of sariya per sq ft for one storey. Put your details in the calculator above; it gives the full list at today's rate. Then add your thekedar's labour rate times the built-up area.
Figures published in 2026 for Muzaffarpur run from about ₹1,750 (NoBroker) to ₹1,896 (InfraLens) per sq ft for a standard house, and none of them says what is inside. Your own figure is your total divided by your built-up area; the calculator shows it once the day's rates are in. More on this: cost per sq ft in Muzaffarpur.
A village house is often brick walls carrying a lenter, with no columns. Choose "Brick walls carry the slab" above: for 1,000 sq ft that is about 350 to 420 bags of cement and 1,500 to 2,200 kg of sariya by the thumb rule, against 400 to 500 bags and 3,500 to 4,500 kg for an RCC frame. Worked out in full: 1000 sq ft house cost and the village brick house.
Yes. 1 katha is 20 dhur. The katha is not one size across Bihar: 1,361.25 sq ft comes from a bigha of 27,225 sq ft, and some converters give 1,500 sq ft for Muzaffarpur. Use the figure on your deed or ask at the registry office, and type it in. The calculator then takes only the covered part of the plot.
No. Boundary wall, borewell, septic tank, soak pit, water tank, doors, windows, grills, sanitaryware, switches and fans are left out. They are listed in not in the list with a page for each.
Every extra foot needs more brickwork round the house and more filling inside it. For a 1,000 sq ft floor, raising it from 1.5 to 3 ft adds roughly 3,300 bricks and 1,350 cft of filling. We found no official plinth height for Muzaffarpur: fix yours from the highest flood your neighbours remember, with a margin, and confirm it with your engineer. How high in a flood area.
Only if the walls and footings are built for a slab from the start. Choose "Ground now, upper later" and price both roofs to see the difference. Sheet-roof house cost.
Labour is kept on its own line. Enter one or two labour-only quotes per sq ft from your thekedars and the calculator multiplies them by the built-up area. Bihar's minimum wage from 1 April 2026 is about ₹436 a day for unskilled and ₹551 for skilled work; market rates are usually above it.
We'll check the quantities with you and send back today's price for each line on WhatsApp. Before dhalai, send photos of the bars and we'll look at them with you.